Detailed Design Preparation WINRIP DOC MPR CTC MPR No.3 2013 03 2013 03 08 00225.
Western I ndonesia National Roads I mprovement Project 16
• Package No. 1 Krui – Biha
: 13 Applicants applied. •
Package No. 2 Pd. Sawah – Sp. Empat : 13 Applicants applied. •
Package No. 3 Manggopoh – Pd. Sawah : 18 Applicants applied. •
Package No. 4 Ipuh – Bantal : 12 Applicants applied.
No Singles JO Legal Name
Participate and Result of the PQ Package
No.1 Package
No.2 Package
No.3 Package
No.4
1 PT. Adhi Karya Persero, Tbk.
Applied NA
NA Applied
2 PT. Adhi Karya - PT. Angkasapuri Konsursindo, JO.
NA Applied
Applied NA
3 PT. Bangun Cipta Konstruksi - PT. Amarta Karya Persero, JO.
Applied NA
NA NA
4 PT. Brantas Abipraya Persero
Applied NA
Applied NA
5 PT. Citra Gading Asritama
NA NA
NA Applied
6 PT. Conbloc Infratecno
Applied NA
Applied NA
7 PT. Duta Graha Indah, Tbk.
Applied Applied
Applied NA
8 PT. Hutama Karya Persero
NA Applied
Applied NA
9 PT. Hutama Karya Persero - PT. Suci Karya Bad inusa, JO.
Applied NA
NA Applied
10 PT. Jaya Konstruksi MP, Tbk. Applied
Applied Applied
Appli ed 11 Kuk Dong Eng. Corp. - PT. Duta Graha Indah, Tbk., JO.
NA NA
NA Applied
12 PT. Multi Structure Applied
Applied Applied
Applied 13 PT. Nindya Karya Persero
NA Appli ed
Applied Appli ed
14 PT. Nindya Karya Persero - PT. Rindang Tigasatu Pratama, JO. Applied
NA NA
NA 15 Pan Asia Corp. - PT. Anugerah Karya Agra Sentosa, JO.
Applied NA
Applied Appli ed
16 PT. PP Persero, Tbk. NA
Applied Applied
NA 17 PT. PP Persero Tbk - PT. Tri Citra Perdana JO.
Applied NA
NA Applied
18 PT. Waskita Karya Persero NA
Applied Applied
NA 19 PT. Waskita Karya Persero - PT. Angkasa Puri Konsursindo, JO.
Applied NA
NA NA
20 PT. Waskita Karya Persero - PT. Daya Mulia Turangga, JO. NA
NA NA
Applied 21 PT. Wijaya Karya – PT. Lubuk Minturun Karya Persada, JO.
NA Applied
Applied Applied
22 PT. Yasa Patria Perkasa NA
NA Applied
NA 23 PT. Angkasa Teknik Raya
NA Applied
Applied NA
24 PT. Bangun Cipta - Barettamuda KSO. NA
NA Applied
NA 25 PT. Bumi Rejo
Applied NA
NA Applied
26 PT. Cipta Karya Prima Mandiri NA
Applied Applied
NA 27 PT. Sumber Batu
NA Applied
NA NA
28 Synohidro Co. Ltd. NA
Applied Applied
NA 29 PT. Telaga Megabuana - PT. Mawatindo Road Construction, JO
NA NA
Applied NA
No. Of applicants submitted the document 13
13 18
12
•
Note : NA = Not Applied for Prequalification
.
All three 3 Procurement Teams or Pokja evaluated all qualification documents submitted by those Applicants. Submission of the Application Evaluation Report AER to the Bank was on
9 May 2012 for two packages Package No.1 and No.4 and on 20 June 2012 for other two packages Package No.2 and No.3. The Bank still reviews the AERs and requested the
Pokja to submit supporting documents. The latest request from the Bank was sent to DGH on 15 March 2013 for board of director and board of commissioner information of the
Government’s Entity participated in the prequalification.
DGH has also completed the draft of consolidated multiple contract ICB Standard Bidding Document for four 4 packages under AWP-1. The draft had been submitted to the Bank on
8 March 2012. The Bank’s comments had been issued on 12 March 2012. The draft of consolidated SBD was revised by DGH accommodating the Bank’s comments and