Detailed Design Preparation WINRIP DOC MPR CTC MPR No.3 2013 03 2013 03 08 00225.

Western I ndonesia National Roads I mprovement Project 16 • Package No. 1 Krui – Biha : 13 Applicants applied. • Package No. 2 Pd. Sawah – Sp. Empat : 13 Applicants applied. • Package No. 3 Manggopoh – Pd. Sawah : 18 Applicants applied. • Package No. 4 Ipuh – Bantal : 12 Applicants applied. No Singles JO Legal Name Participate and Result of the PQ Package No.1 Package No.2 Package No.3 Package No.4 1 PT. Adhi Karya Persero, Tbk. Applied NA NA Applied 2 PT. Adhi Karya - PT. Angkasapuri Konsursindo, JO. NA Applied Applied NA 3 PT. Bangun Cipta Konstruksi - PT. Amarta Karya Persero, JO. Applied NA NA NA 4 PT. Brantas Abipraya Persero Applied NA Applied NA 5 PT. Citra Gading Asritama NA NA NA Applied 6 PT. Conbloc Infratecno Applied NA Applied NA 7 PT. Duta Graha Indah, Tbk. Applied Applied Applied NA 8 PT. Hutama Karya Persero NA Applied Applied NA 9 PT. Hutama Karya Persero - PT. Suci Karya Bad inusa, JO. Applied NA NA Applied 10 PT. Jaya Konstruksi MP, Tbk. Applied Applied Applied Appli ed 11 Kuk Dong Eng. Corp. - PT. Duta Graha Indah, Tbk., JO. NA NA NA Applied 12 PT. Multi Structure Applied Applied Applied Applied 13 PT. Nindya Karya Persero NA Appli ed Applied Appli ed 14 PT. Nindya Karya Persero - PT. Rindang Tigasatu Pratama, JO. Applied NA NA NA 15 Pan Asia Corp. - PT. Anugerah Karya Agra Sentosa, JO. Applied NA Applied Appli ed 16 PT. PP Persero, Tbk. NA Applied Applied NA 17 PT. PP Persero Tbk - PT. Tri Citra Perdana JO. Applied NA NA Applied 18 PT. Waskita Karya Persero NA Applied Applied NA 19 PT. Waskita Karya Persero - PT. Angkasa Puri Konsursindo, JO. Applied NA NA NA 20 PT. Waskita Karya Persero - PT. Daya Mulia Turangga, JO. NA NA NA Applied 21 PT. Wijaya Karya – PT. Lubuk Minturun Karya Persada, JO. NA Applied Applied Applied 22 PT. Yasa Patria Perkasa NA NA Applied NA 23 PT. Angkasa Teknik Raya NA Applied Applied NA 24 PT. Bangun Cipta - Barettamuda KSO. NA NA Applied NA 25 PT. Bumi Rejo Applied NA NA Applied 26 PT. Cipta Karya Prima Mandiri NA Applied Applied NA 27 PT. Sumber Batu NA Applied NA NA 28 Synohidro Co. Ltd. NA Applied Applied NA 29 PT. Telaga Megabuana - PT. Mawatindo Road Construction, JO NA NA Applied NA No. Of applicants submitted the document 13 13 18 12 • Note : NA = Not Applied for Prequalification . All three 3 Procurement Teams or Pokja evaluated all qualification documents submitted by those Applicants. Submission of the Application Evaluation Report AER to the Bank was on 9 May 2012 for two packages Package No.1 and No.4 and on 20 June 2012 for other two packages Package No.2 and No.3. The Bank still reviews the AERs and requested the Pokja to submit supporting documents. The latest request from the Bank was sent to DGH on 15 March 2013 for board of director and board of commissioner information of the Government’s Entity participated in the prequalification. DGH has also completed the draft of consolidated multiple contract ICB Standard Bidding Document for four 4 packages under AWP-1. The draft had been submitted to the Bank on 8 March 2012. The Bank’s comments had been issued on 12 March 2012. The draft of consolidated SBD was revised by DGH accommodating the Bank’s comments and