Road Safety Audit WINRIP DOC MPR CTC MPR No.3 2013 03 2013 03 08 00225.

Western I ndonesia National Roads I mprovement Project 26 5 FINANCIAL MANAGEMENT INFORMATION SYSTEMS

5.1 Draw Downs and Future Costs

Details of the disbursements already made from the loan are listed in the following sub section.

5.2 Disbursement

The total disbursement from the loan to the end of March 2013 was USD 2,207,915.00 equivalent to approximately 0.88 of the loan funds. The total expenditure to date measured in the term of the World Bank commitment, not including the Special Account advance, is shown in Appendix C. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of March 2013. Category Description Loan Amount US Totals Disbursed to End March in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 2 Part 2 Implementation Support 16,000,000.00 674,177.03 4.21 3 Part 3 Road Sector Institutional Development 1,000,000.00 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 LN 8043 DA-A 1,533,737.97 Original Loan Amount 250,000,000.00 2,207,915.00 0.88 Western I ndonesia National Roads I mprovement Project 27 5.3 Management Information System 5.3.1 General Overview The Management Information System tasks will include the followings: 1 Information System a. Develop and manage a database system to store soft copy documents into a file storage server. b. Establish a Document Management System DMS to provide: • Letter Database System, used to record all information of incoming and outgoing letter. • Document Library System, used to record all information of hard copy documents then store it into library shelves. c. Create and maintain a WINRIP official website. d. Develop and update a Geographic Information System GIS of spatial and roads information that overlay into Google Maps. e. Develop and manage a Financial Management Information System FMIS, the web based application to monitoring financial progress. f. Develop and manage a Progress Monitoring System PMS, the web based application to monitoring physical progress. g. Provide a Complaint Handling System CHS, used and support the ACAP activities to accommodate complaints from the public via sms gateway, email and website. 2 Data Collection and Document Upload a. Collecting data and updating list of data catalog every month. b. Uploading documents into a file storage server. 3 Technical and Computer Troubleshooting a. Setting up and manage cable network of local area network and internet connection. b. Setting up and manage hardware problem of the computer, printer, copier and phone. c. Software installation and cleaning up of computer virus.

5.3.2 Database

A typical workflow in management of incoming and outgoing data will be divided into 3 types of data handling, below: 1. Hardcopy, the document is stored in a rack. 2. Soft files, saved in the File Storage Server. 3. Data information, inputted in database applications.