Monthly Progress Report August 2013 Western I ndonesia National Roads I mprovement Project 32 6 PROJECT PERFORMANCE 6.1 World Bank and GOI Compliance 6.1.1 World Bank Missions No World Bank missions visited Indonesia during April 2013.

6.1.2 Performance Indicators

GOI and the World Bank have agreed on a set of Key Performance Indicators KPIs to measure the project’s performance in achieving its stated development objectives. These KPIs are provided in the World Bank’s Project Appraisal Document PAD, together with baseline data and targets. The annual targets for KPIs that are indicated in the Project Appraisal Document are based on the initial Project Implementation Schedule as shown in Appendix H. The CTC is concentrating on the establishment of precise definitions, calculation methods and data collection procedures to monitor the KPIs. 6.2 Implementation Support Components 6.2.1 Core Team Consultant CTC The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, information management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of the anti-corruption action plan, support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation. The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. PerentjanaDjaja, Yongma Engineering Co.Ltd., and PT. EpadasconPermata Engineering Consultant. The main CTC activities during August 2013 included: • Continue assistance to PMU as and when required. • Prepare and submit Monthly Progress Report for July 2013. • Site Visit for 1 Package No. 15 : Sibolga - Bts Tapsel of AWP- 2 in North Sumatera • Submission of Intern Financial Report IFR QR-2 Periode April – Juni 2013 WINRIP Loan IBRD 8043 -ID • Presentation by the Senior Highway Engineer and the Highway Engineer on review results of DED Package 05 Simpang Rampa – Poriaha and Package 15 Sibolga – Batas Tapsel. • Submission of LARAP Report of Package No. 5 Sp. Rampa-Poriaha and No.17 Sp. Gn Gemala – Pugung Tampak • Meeting Amendment No. 1 CTC WINRIP Monthly Progress Report August 2013 Western I ndonesia National Roads I mprovement Project 33 The following table summarized the CTC personnel field activities during August 2013. Date Position Destination Purpose 1-2 August 2013 Environmental Specialist Lampung Action Plan for LARAP and Land Acquisition 19-20 August Environmental Specialist Palembang Document Preparation Training for Consultants LARAP Balai 3 20-21 August 2013 Quality Assurance Specialist Padang Orientation Project with DSC WINRIP, Discussion about Quality Assurance Modul 21 -22 August 2013 Senior Highway Engineer, Senior Road Safety Audit Engineer, and Highway Engineer Medan Re-visit The Link Sibolga-Batas Tapsel to confirmed the Final DED

6.2.2 Design and Supervision Consultant DSC

The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West Sumatra. DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March 2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.

6.2.3 Road Sector Institutional Development

This component consists of technical assistance for capacity building for the new environmentrisk mitigation and road safety unit to enhance its capacity for disaster risk assessment and planning, risk mapping of land-slides, coastal erosion, earthquake and floods, analysis of alternative road designs for road segments passing through critical environmental assets and vulnerable areas. It is planned so far that there will be three 3 consultants services for: • Capacity Building of Disaster Risks Reduction • Capacity Building for Environmental Management • Capacity Building for Road Safety