All activities which have undertaken during this month Current status of the project for technical field as of 31 August 2013.

Monthly Progress Report August 2013 Western I ndonesia National Roads I mprovement Project 40 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 16 Seblat – Ipuh Link No.010.0 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed completed ongoing Full Technical Review is not completed yet by CTC 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018

6.6 Environmental and Social Impact Issues

• Submission LARAP Study Report for Package No. 05 : Sp Rampa – Poriaha and Package No. 17 : Sp. Gunung Kemala – Pugung Tampak • Received LARAP from Balai Package No. 10 : Simpang Empat Air Balam, Package No. 8 : Bts Kota Pariaman – Manggopoh, and Package No. 12 : Kambang - Indrapura

6.7 Management Information Systems

The Information Management Specialist has been mobilized. The activity for management information system will be reported soon.

6.8 Quality Assurance

Quality Assurance Engineer has been mobilized now. But the quality assurance activities for the project can’t be reported due to the end of August 2013, there has been no work activity at the beginning. Monthly Progress Report August 2013 Western I ndonesia National Roads I mprovement Project 41 6.9 Project Risks and Mitigation Measures 6.9.1 Risks Related to Delays Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the procurement of AWP-2 and AWP-3 sub-projects. As discussed previously above, the DED of several subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. The CTC has then been instructed by DGH to review the DEDs of seven packages completed by the P2JNs package 5, 6, 11, 13, 15, 17 and 19.

6.9.2 Financial Risks

The following factors will be monitored during implementation of the loan project. • Loan Amount • Actual Tender Prices • Price Adjustment • Currency Fluctuation • Current Estimated Situation No risk was detected until preparation of this report since the main program of the loan civil works implementation has not yet been started with contract sign.

6.9.3 Risks Related to Quality

The quality of work is inherently tied to the competence of the Contractors and the diligence of the Supervision Teams. The competence or otherwise of contractors shall be considered at the time of bid evaluation and prior to the award of any contract. The quality of supervision however is influenced by the following factors: • Ensuring that supervision staff levels are fully manned with competent, honest, qualified and experienced personnel. • The provision of properly equipped laboratories with properly trained operators for each package. Package supervision comes under the responsibilities of the immediate supervision teams and the relevant DSC but the Quality Assurance Engineer from CTC, when mobilized, will periodically monitor their performance.