Monitoring Report of the LARAP Package No.16 Monitoring Report of the LARAP Package No.17 Monitoring Report of the LARAP Package No.18 Monitoring Report of the LARAP Package No.19

Western I ndonesia National Roads I mprovement Project 4 - 15

15. Monitoring Report of the LARAP Package No. 15

: Sibolga Bts. Tapsel Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. B. Pending Issues, Concern and Actions a 1068 from total 1148 PAP is under negosiationcompensation process. b Monitoring Report No.1 for LARAP implementation for compensation of 80 out of the 1448 PAP still to be prepared by SATKER RIN North Sumatra. C. Update during this reporting month of May 2015 a 80 from total 1448 PAP already received compensation payment from Satker PJN North Sumatera.

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • World Bank issued No Objection Letter NOL on Monitoring Report No.1 for LARAP implementation. B. Pending Issues, Concern and Actions a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared. b LARAP Implementation is underway for the remaining 311 PAP be allocated 2015 national budget and schedule to be settled on June to July 2015. C. Update during this reporting month of May 2015 a No update this period.

17. Monitoring Report of the LARAP Package No.17

: Sp. Gunung Kemala Pg. Tampak Province : Lampung A. Previous Status : • World Bank approved the corrected LARAP documents on November 12, 2013 B. Pending Issues, Concern and Actions a Still to be submitted is the implementation report from Satker of the land acquisition implementation. C. Update during this reporting month of May 2015 a Appraisal of affected assets buildings, houses, plant and other obstructions by Independent Appraisal Team is on-going. Western I ndonesia National Roads I mprovement Project 4 - 16

18. Monitoring Report of the LARAP Package No.18

: Mukomuko Bts. Sumbar Province : Bengkulu A. Previous Status : • Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of May 2015 a Still no update during this period. b Proposed to be replaced.

19. Monitoring Report of the LARAP Package No.19

: Lais - Bintunan Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation • World Bank issued No Objection Letter NOLon Monitoring Report No.1 for the LARAP implementation. B. Pending Issues, Concern and Actions a Remaining 177 PAP to be compensated from the 2015 National Budget on June to July 2015. C. Update during this reporting month of May 2015 a No update this period.

20. Monitoring Report of the LARAP Package No. 20