Western I ndonesia National Roads I mprovement Project 4 - 13 a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of May 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung A. Previous Status : • Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of May 2015 a Nothing to report this period. b Proposed to be replaced.

10. Monitoring Report of the LARAP Package No. 10

: Sp. Empat Sp. Air Balam Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of May 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11

: Bantal - Mukomuko Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the World Bank. B. Pending Issues, Concern and Actions a Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget. Payments are scheduled in June to July 2015. C. Update during this reporting month of May 2015 Western I ndonesia National Roads I mprovement Project 4 - 14 a No Update this period.

12. Monitoring Report of the LARAP Package No. 12

: Kambang - Indrapura Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. B. Pending Issues, Concern and Actions a No allocated budget to pay land acquisition in the 2014 budget of the Local Government. Compensation payments to be allocated from the 2015 budget. C. Update during this reporting month of May 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.