Monitoring Report of the LARAP Package No. 6 Monitoring Report of the LARAP Package No. 7 Monitoring Report of the LARAP Package No. 8

Western I ndonesia National Roads I mprovement Project 4 - 12 a Still to be submitted is the implementation report from Satker of the completed relocation of the kiosk. C. Update during this reporting month of May 2015 a Monitoring Report for the concerning the completed relocation of the kiosk still to be prepared for submission to World Bank. b No Update this period

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for implementation. • Monitoring Report concerning the compensation payment for 546 out of 602 PAP was given No Objection Letter NOL on March 23, 2015. B. Pending Issues, Concern and Actions a Remaining 56 from the 602 PAP will be resolved on June to July 2015. C. Update during this reporting month of May 2015 a No update this period

7. Monitoring Report of the LARAP Package No. 7

: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank. B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for review. b Implementation cost of LARAP will be included by Local Government in the 2015 budget. C. Update during this reporting month of May 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are completed. Appraisal of affected assets are underway.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions Western I ndonesia National Roads I mprovement Project 4 - 13 a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of May 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

9. Monitoring Report of the LARAP Package No. 9