Western I ndonesia National Roads I mprovement Project 1 - 4
1.3 World Bank Implementation Review Mission and Site Visit
During the period May 2015, there was no implementation review mission nor regular Monthly Meeting to review implementation progress and monitoring the key activities on the  Agreed Key
Actions Plan .
However, CTC s and World Bank s environmental specialists carried out a joint mission to Package No.2 Sp. Empat
Pd. Sawah and Package No.3 Manggopoh Padang Sawah to follow up on the
environmental,  health  and  safety  EHS  measures  that  the  Contractors  has  taken  in  response  to the findings of World Bank Safeguard Portfolio Review in February 2015.
Likewise,  the  Technical  and  Financial Audit  Consultant  TFAC  conducted  introductory  meetings with  all  SATKER s  and  all  PPK s  in  Medan  and  Bengkulu  on  May  22,  2015  and  May  25,  2015,
respectively to explain the TFAC s concept regarding the financial and technical audits of the sub- projects.
Lastly, technical audits were carried out for Contract Package No.4 Ipuh Bantal on May 26
29, 2015 with an opening meeting on the 1
st
day, followed by the actual site audit and closing meeting on the last day of the schedule.
1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement
The current  status  of Contract  Packages which  are  under final procurement stage  are  as follows :
1. Package 17 Sp. Gunung Kemala
Pugung Tampak AWP-3.
This  sub-project  is  under  implementation  schedule AWP-3.  The  project  roadline  is located in the Province of Lampung having an approximate length of 36.80 kilometers.
The  Contract  Package  is  procured  thru  the  Prequalification  and  International Competitive Bidding ICB procurement method.
As  mentioned  in previous Monthly  Progress  Report, World  Bank  already  issued  the disbursement form Form 384.
Notice To Proceed to commence the Works is still to be issued subject to completion of the acquisition of Right of Ways ROW and LARAP implementation.
2. Package 13 Sp. Rukis
Tj. Kemuning AWP-2
This  sub-project  is  under  implementation  schedule  AWP-2.  The  project  roadline  is located in the Province of Bengkulu having an approximate length of 56.30 kilometers.
The  Contract  Package  is  procured  thru  the  Prequalification  and  International Competitive Bidding ICB procurement method.
As previously metioned in the previous monthly report, World Bank already issued the disbursement form Form 384.
Notice To Proceed to commence the Works is still to be issued subject to completion of the acquisition of Right of Ways ROW and LARAP implementation.
3. Packages 5 Simpang Rampa
Poriaha AWP-2
This  sub-project  is  under  implementation  schedule  AWP-2.  The  project  roadline  is located  in  the  Province  of  Sumatera  Utara  having  an  approximate  length  of
9.70 kilometers.
The  Contract  Package  is  procured  thru  the  Prequalification  and  International
Western I ndonesia National Roads I mprovement Project 1 - 5
Competitive Bidding ICB procurement method. The Contract was signed on March 17 2015 and on May 4, 2015 World Bank confirmed
the signed  Contract Agreement  with the issuance of Form 384 for disbursement.
4. Package No.15 Sibolga
Batas Tapsel AWP-3
This sub-project is included in the implementation schedule AWP-3. The Project road is 36 kilometers long and located in the Province of Sumatera Utara.
The  Contract  Package  is  procured  thru  post  qualification  criteria  and  International Competitive Bidding ICB method using the Full e-Procurement System.
World  Bank concurred  the Bid  Evaluation  Reports  BER on  May  7,  2015  and recommendation  to  award  the  Contract  to  the  lowest  responsive  bidder  PT.
Pembangunan  Perumahan  Persero  in  the  amount  of  Rp.260,100,000,011 with  the issuance of No Objection Letter NOL.
5. Package No.7 Indrapura - Tapan AWP-2