Civil Works Progress WINRIP DOC MPR CTC MPR No.49 2017 01 20170131 00445

Western I ndonesia National Roads I mprovement Project 4 - 5 Package No. 5 : Sp. Rampa Poriaha The progress of this month is achieved of only 0.76 against the scheduled 11.50. For catching up the delayed progress, the contractor has to increase the production of the aggregate materials for Asphalt Pavement, Granular Pavement. ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap Ps. Pedati The completion date of this package is 28, January 2017. Actual overall progress as of 25, January 2017 has been achieved with 97.03 which is still less 2.97 against the scheduled. The asphalt pavement of AC-wearing course has been completed and the remain works are a few of should final layer and pavement markings, sign, post partially. Hence, the works are to be completed substantially for the taking-over. ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura Tapan During this month, the work items which leaded negative progress were mainly Drainage works, Asphalt pavement. The delayed progress has been bigger negatively than the last month, -4.53 of the last month to -9.57 on this month. In order to catch-up the delayed progress, the contractor plans to install an additional crushing plant on the Base Camp area. Certain shortage of Abu-Batu could be expected in normal as additional crushed plant is operated. ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh For this month s work progress as well from the commencement of the project, the contractor maintains ahead progress, 37.93 against the scheduled 35.38. As mentioned previously, preparatory works, namely production of Aggregate materials, Granular pavements, earth works are pretty well executed. Thus comming month progress as well is to be in positive position. On the other hand, unsettled land acquisition, 5.253m is still in difficulties to find the solution. It is expected to be settled up to March 2017. ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko For this month s work progress is only 1.21 achieved due to the same reason of the last month for delayed progress. The negative slippage rate is raised up again up to -11.96 against the last month -9.81. In order to improve the progress of Asphalt pavement works, the contractors had purchased the Abu-Batu dust 2.200 Ton from Paadang which is the one of main reason for the delayed progress of Asphalt Western I ndonesia National Roads I mprovement Project 4 - 6 Pavement. The contractor urges the Time Extention of 3.5 Months, to the completion of the work. For more details of the Contract Package, refer to ANNEX P-11 Executive Summary Report . Package No. 12 : Kambang - Indrapura The actual progress as of this month is only 4.03 since 8 months elapsed from the COW against the scheduled 15.87. Furthermore, this month progress is only 0.01 either. The main reason for the srious delay that not only the contractor s construction management system and organization of staffs are totally collapsed but also the supports and concern of the contractor s head office to this project are likely not made up to now. For instance, the contractor s General Superintendant has been absent for 3 months and it seems there are no experienced and or qualified staffs on the site. The only hopeful site situation is that plantiful natural river stones are stockpiled in the Base Camp and the quarry site is located in only 2 Km from the Base Camp. Details of the Contract Package are shown in ANNEX P-12 Executive Summary Report . Package No. 13 : Sp. Rukis Tj. Kemuning The progress of this month 8.48 has been leaded by the asphalt pavement affected 100. Some of the granular pavement works on the strecth sta. 43 KM~56 km are constructing but not completed for measuring the work progress. At this stage, the contractor has a lot of working areas for asphalt pavement for wearing course apprx. 15 Km thus, within a few months, they will have a positive progress from the pavement for the time being. Accordingly, the big slippage rate -41.51 also could be improved for coming several months. The most considerable elemants to reach the successful completion of this project are how to settled the land acquisition on the strecth sta. 25 km ~ 43 Km 18 Km long earlier. Details of the work progress are shown in ANNEX P-13 Executive Summary Reports. Package No. 14: Painan - Kambang The work progress of this month is only 2.02 against the scheduled 4.18 according to the revised schedule to be completed as of Dec. 2017. The accumulated slippage rate will be -4.09. At this present, the work progress is only done from the strecth sta 0 Km~12 Km. The contractor has to develope the other working areas in order to catch up the delayed progress. ANNEX P-14 Executive Summary Report shows the complete details of the project. Package No. 15: Sibolga Bts. Tapsel During this month, the progress is achieved of 13.73 against the scheduled 5.5. Therefore, the slipagge rate as well has been reduced up to -15.7 from -23.93.