Western I ndonesia National Roads I mprovement Project 4 - 3
4.4 Civil Works Progress
Activities done during this month on the on-going construction packages were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular
pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction,
finalization of Field Engineering surveys and mobilization of resources of the newly started contract package.
The four 4 contract packages under implementation program AWP-1 were already completed and now under defects liability period for two 2 years since the issuance of TOCs.
Under the implementation program AWP-2 and AWP-3, there are currently thirteen 13 contract packages that are on-going construction implementation. Physical progress of five 5 of the packages are lagging far
behind schedule with negative slippages of -41.51 and -15.68, -12.80, -11.96, -11.84 while progress for the other Six 6 packages are still slightly on or behind schedule, one 1 packages are on ahead
schedule and the rest one has just started on Nov 8,2016 .
Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2.
Following are brief status of the on-going construction contract packages :
Package No. 1 : Biha Krui
The contract package is completed on January 20, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
A more detailed previous status during the whole duration of the contract implementation of this Package is presented in ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge
The contract package is completed on April 14, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the contract implementation of the Contract Package.
Package No. 3 : Manggopoh Padang Sawah
The contract package is completed on March 17, 2016 and provisionally handed over to the Employeer on March 17, 2016 and currently under Defects Notification Period until after two 2 years reckoned from
the issuance of the TOC.
A more detailed status of the project progress during the whole duration of the contract implementation are shown in ANNEX P-3 Executive Summary Report .
Package No. 4 : Ipuh Bantal
The contract package is completed on May 31, 2016 and provisionally handed over to the Employeer on May 31, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the
issuance of the TOC.
Shown in ANNEX P-4 Executive Summary Report showing the details and status of the project.
Western I ndonesia National Roads I mprovement Project 4 - 4
Table 4.2
Program Contract
Package Contractor
Name of Road Target Progress
Schedule Ending January 2017
Actual Progress Accomplished
Slippage Time Elapsed
Remaining Time
Remarks
AWP-1 1
PT. Jaya Konstruksi Manggala Pratama Tbk
Biha - Krui -
- -
- Completed
PHO : Jan 20, 2016
2 PT. Jaya Konstruksi Manggala
Pratama Tbk Padang Sawah
Sp.Empat incl.Air Gadang
- --
- -
Completed PHO : April 14, 2016
3 PT. Jaya Konstruksi Manggala
Pratama Tbk Manggopoh
Padang Sawah
- -
- -
Completed PHO : Mar 17, 2016
4 PT. Waskita Karya and PT.
Mulya Turangga JO Ipuh - Bantal
- -
- -
Completed PHO : May 31, 2016
AWP-2 5
PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha
53.49 43.50
-9.99 76.93
176 CD Based on revised contract time
and schedule 6
PT. Waskita Karya Tbk Ps. Pedati
Kerkap 100
97.03 -2.97
99.56 3 CD
Based on 2nd revised contract time and schedule
7 PT. Adhi Karya
Indrapura - Tapan 50.84
41.27 -9.57
65.50 217 CD
Based on original contract time and schedule
8 PT. PPPT. Statika Mitra J.O
Bts. Kota Pariaman Manggopoh
35.38 37.93
2.55 47.53
340 CD Based on original contract
time and schedule 11
PT. Hutama Karya PT. DMT Mukomuko - Bantal
99.45 87.49
-11.96 97.64
17 CD Based on original contract
time and revised schedule 12
PT. LancarjayaPT. Cahaya T.A. JO
Kambang Indrapura
15.87 4.03
-11.84 42.08
340 CD Based on original contract
time and revised schedule 13
PT. Waskita Karya Persero Tbk
Sp. Rukis Tj. Kemuning
82.62 41.11
-41.51 76.91
166 CD Based on original contract
time and schedule
AWP-3 14
PT. Yasa PT. Conbloc JO
Painan Kambang
10.05 5.96
-4.09 33.98
340 CD Based on revised contract
time and schedule 15
PT. Pembangunan Perumahan Persero
Sibolga Bts. Tapsel
49.94 34.25
-15.68 55.96
340 CD Based on revised contract
time and schedule 16
PT Yasa-Multi Structure, Jo Seblat Ipuh
0.57 0.41
-0.16 12.40
551 CD
17 PT. Jaya Konstruksi Manggala
Pratama Tbk Sp. Gn Kemala
Pg. Tampak
61.80 49.01
-12.80 70.79
210 CD Based on original contract
time and schedule 19
PT. Rodatekindo Purajaya Lais - Bintunan
100 100
- -
- Completed
PHO : June 30, 2016
20 PT. Nindya Karya
Lubuk Alung Sicincin
19.58 16.95
-2.63 30.04
340 CD Based on revised contract time
21 PT. Multi Structure
Lubuk Alung Kuraitaji
20.07 13.38
-6.69 30.04
340 CD Based on revised contract time
Under defects liability period for 720 calendar days.
Western I ndonesia National Roads I mprovement Project 4 - 5
Package No. 5 : Sp. Rampa Poriaha
The progress of this month is achieved of only 0.76 against the scheduled 11.50. For catching up the delayed progress, the contractor has to increase the production of the aggregate
materials for Asphalt Pavement, Granular Pavement.
ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap
Ps. Pedati
The completion date of this package is 28, January 2017. Actual overall progress as of 25, January 2017 has been achieved with 97.03 which is still less 2.97 against the scheduled.
The asphalt pavement of AC-wearing course has been completed and the remain works are a few of should final layer and pavement markings, sign, post partially. Hence, the works are to be completed substantially
for the taking-over.
ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura
Tapan
During this month, the work items which leaded negative progress were mainly Drainage works, Asphalt pavement.
The delayed progress has been bigger negatively than the last month, -4.53 of the last month to -9.57 on this month.
In order to catch-up the delayed progress, the contractor plans to install an additional crushing plant on the Base Camp area.
Certain shortage of Abu-Batu could be expected in normal as additional crushed plant is operated.
ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh
For this month s work progress as well from the commencement of the project, the contractor maintains ahead progress, 37.93 against the scheduled 35.38.
As mentioned previously, preparatory works, namely production of Aggregate materials, Granular pavements, earth works are pretty well executed. Thus comming month progress as well is to be in positive
position.
On the other hand, unsettled land acquisition, 5.253m is still in difficulties to find the solution. It is expected to be settled up to March 2017.
ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko
For this month s work progress is only 1.21 achieved due to the same reason of the last month for delayed progress.
The negative slippage rate is raised up again up to -11.96 against the last month -9.81. In order to improve the progress of Asphalt pavement works, the contractors had purchased the Abu-Batu
dust 2.200 Ton from Paadang which is the one of main reason for the delayed progress of Asphalt