Monthly Progress Report January 2017
Western I ndonesia National Roads I mprovement Project 7 - 2
c The budget for land acquisition of Packages 05, 12, 13, 14, 15, and 17 have been allocated in fiscal year 2017. The PIU is requested to remind the PPK to allocate the fund
for splitzing programs especially for provinces of Lampung, Bengkulu, and North Sumatra.
d The PPK is under preparation of amendment which is included with an additional contract value and Time Extention.
e In accordance with the results of TFAC inspection on site, WB had agreed principally in verbal and the PPK requested the Pre-Audit of BPKP for the legal aspects in term of
making amendment after TOC. f
Contract Amendment and technical justification of Package 03 related to the final quantity is being reviewed by the PIU and PMU. CTC and PMU will consult to the WB s
Procurement Specialist related to the legal aspects of the contract in terms of making amendment after the TOC.
g If the issue of land acquisition in Package 15 cannot be resolved, roadwork in that segment of the road will use the existing ROW.
h Any changes to the contract must follow the instructions set forth in the Project Management Manual of WINRIP
i Proposed extension of the loan closing date
j The repairing work done by gabion was completed.
k Information on related Satker that the repair work being carried out by the disaster fund.
l It has been discussed with the Bank in terms of the possibility of financing such works
within the defect notification period. WB requires data on the implementation of the road construction and design for handling the road settlement.
m CTC has written to DSC to evaluate the entire stone crusher in WINRIP and find out causes and remedies.
Monthly Progress Report January 2017
Western I ndonesia National Roads I mprovement Project 8 - 1
8 CORRESPONDENCES
During the period the CTC received and issued letters. Lists of letters received and issued are shown in Appendix J.