Western I ndonesia National Roads I mprovement Project 4 - 31
a. AWP-1 sub-projects Packages 1, 2, 3 and 4 b. AWP-2 sub-projects Packages 5, 6, 7, 8, 10, 11, 12 and 13
c. AWP-3 sub-projects Packages 14, 15, 16, 17, 19, 20 and 21 Road Safety Audit at detailed design stage is to identify the road safety weaknesses in design drawings
through site visiting, review of design drawings and official meeting with stake holder. Road Safety Audit report is the recommendation for improvement of road safety.
Road Safety Audit at Construction stage or Traffic Management and Safety Monitoring is to check the performance of contractors related to the implementation of application management and traffic
safety in the field. Road Safety Audit at pre-opening stage is to ensure that the road has been built as designed and to
identity any safety issues that may have been missed through the design procees. The overall progress of the different stages of Road Safety Audit are shown in
Appendix B.
Western I ndonesia National Roads I mprovement Project 5 - 1
5 FINANCIAL MANAGEMENT INFORMATION SYSTEMS
5.1 Draw Downs and Future Costs
Details of the disbursements already made from the loan are listed in the following sub section.
5.2 Disbursement
The total disbursement by World Bank from the loan to the end of January 2017 was USD 102,340,497.30 equivalent to approximately 40.94 of the loan funds. A total
disbursement of USD 1,160,260.33 was made during the month of January 2017 for the
payment Interim Payment Certificates for the Statement of Work Accopmplished under Category 1 Part 1 of the loan agreement.
The total expenditure to date measured in the term of the World Bank commitment, not
including the Special Account advance, is shown in Appendix C. The following table
summarizes the individual disbursements as calculated by CTC but retaining the total
disbursement from Client Connection at the end of January 2017.
Category Description
Loan Restructuring Amount USD
Totals Disbursed to End January 2017 in
USD Disbursed
1
Part 1 Betterment and
Capacity Expansion of National Roads.
220,400,000.00
95,550,391.47 43.35
2
Part 2
Implementation Support 17,000,000.00
6,790,105.83 39.94
3
Part 3
Road Sector Institutional Development
4
Part 4
Contingency for Disaster Risk Response
Unallocated 12,600,000.00
Original Loan Amount
250,000,000.00
102,340,497.30 40.94
5.3. Management Information System
5.3.1. General Overview
The Management Information System tasks are as follows below:
1 Information System a. Develop and manage the File Storage as database system to store soft copy
documents into the server.
b. Establish the Document Management System DMS to provide:
• Letter Database System, used to record all information of incoming and
outgoing letter.