Monitoring Report of the LARAP Package No. 7

Western I ndonesia National Roads I mprovement Project 4 - 21

12. Monitoring Report of the LARAP Package No. 12

: Kambang - Indrapura Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016. B. Pending Issues, Concern and Actions a PPKSatker PJN II West Sumatera continue the appraisal and payment processing of the remaining PAP. C. Update during this reporting month of October 2016 a Currently there are 28 Km out of the total length of 56 Km, that land aquisition is not needed. b Monitoring Report for compensation payment progress of 60 PAPs is under submission to WB from PMU. c Total PAP = 2,337; Compensated = 601; Percent complete = 25.7.

13. Monitoring Report of the LARAP Package No. 13

: Sp. Rukis Tj. Kemuning Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1. • World Bank issued on October 13, 2015 No Objection Letter NOL on the monitoring Report No.2. • Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WB which was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8, 2016. • Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WB which was submitted on October 6, 2016 B. Pending Issues, Concern and Actions a Compensation payments for the remaining 2,295 PAPs being done by Satker C. Update during this reporting month of October 2016 a DIPA 2016 amounting to RP. 10 Billion was ready b Total PAP = 3,198; Compensated = 903; Percent complete = 28.3. c Monitoring Report of the payments progress for 333 PAPs is under submission to WB d The payment for about 2,329 affected persons APs wil complete in the end of this year will complete and the remaining Aps will be continued in FY2017. The budget needed for the FY2017 payment is around 4.5 billion IDR.