Current Implementation Situation Civil Works

Western I ndonesia National Roads I mprovement Project 1 - 3 Revised : 4 Nov 2016 Length Cti on Km Peri od J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Core Team Consultant CTC 40 mth IMPLEMENTATION Time extension for sevices Design Supervision Cslt DSC 42 mth IMPLEMENTATION Time extension for sevices TA for Dev.of Sl ope Sta bi l i za ti on, Desi gn M a na gement 1 Krui - Biha 25,00 21 mth 8 Jan14 2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan14 3 M anggopoh - Padang Sawah 32,00 24 mth 6 Jan14 4 Ipuh - Bantal 42,40 24 mth 10 Jan14 5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun15 8 Dec16 11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb15 11 Feb17 13 SP RUKIS - TJ KEMUNING 56,30 24 mth 11 Feb17 17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep15 23 Agt17 6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar15 31 Aug16 19 LAIS - BINTUNAN 11,60 10 mth 11 Mar15 CONSTRUCTION 300+125+53 days 30 Jun 16 15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov15 7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec15 30 Agt17 8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth PROC 23 Mar16 10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth 12 KAMBANG - INDRAPURA 55,20 24 mth 14 PAINAN KAMBANG 31,50 21 mth PROC 13 Aug16 16 SEBLAT IPUH 34,50 21 mth CONSTRUCTION 20 LUBUK ALUNG SICINCIN 14,60 18 mth 1 Sep16 21 LUBUK ALUNG KURAITAJI 16,80 18 mth 1 Sep16 Original target : 715,60 km ENVIRONMENT SOCIAL SAFEGUARD 1st Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study Road Safety Owners Estimate Appraisal Public Consultation Procurement Sign Contr Bid Document LARAP Implementation Preparation for Commencement of Work Standard Biding Document Review DED RS PQ Review DED RS PQ PQ Review DED RS Review DED RS PROC CONSTRUCTION 720 days CONSTRUCTION 720 days 22-Jul-15 PQ PROC ICB ICB ICB ICB ICB CONSTRUCTION 640 + 93 days 14-Apr-16 PROC 17-Mar-16 CONSTRUCTION 540 days CONSTRUCTION 730 + 105 days CONSTRUCTION 730 + 75 days CONSTRUCTION 730 + 90 days 31-Mei-16 Pack PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018 PQ RS Proc COW SBD DED OE BD DED NCB NCB DED NCB NCB NCB Review DED RS Review DED RS SBD OE + BD RSA REVISED DED OE BD DED RSA REVISED DED OE BD SBD OE + BD DED RSA REVISED DED OE BD DED ICB RSA REVISED DED OE BD Review DED RS SBD OE + BD 6-Nov-12 19-Jun-13 PROC PROC DED Rev-DED RS ICB ICB NCB NCB DED PROC CONSTRUCTION 720 days ICB ICB ICB ICB PROC CONSTRUCTION 810 - 37 days DED CONSTRUCTION 630 days 23-Mei-16 CONSTRUCTION 720 - 132 days 30-Des-17 30-Des-17 PROC PROC to be canceled CONSTRUCTION 720 - 71 days Rev-DED RS Rev-DED RS Rev-DED RS 31-Des-17 30-Des-17 PROCUREMENT IMPLEMENTATION 31-Des-17 31-Des-17 31-Des-17 CONSTRUCTION 450+90 days 31-Des-17 CONSTRUCTION 540 - 53 days 31-Des-17 CONSTRUCTION 540 - 53 days CONSTRUCTION 630 - 114 days Actual Implementation Timeline of WINRIP Western I ndonesia National Roads I mprovement Project 1 - 4

1.2 Disbursement

Loan Allocation and Percent Disbursement To Date REF 1.25 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 Month Co m pl et e Actual Expenditure USD 78.31 mil 31.33 WINRIP ACTUAL PROGRESS UP TO OCTOBER 2016 AND FORECAST UP TO JUNE 2018 ACTUAL Oct 2016 Original Forecast Forecast Expenditure Rev USD 58.18 mil 23.27 Forecast Oct 2016 Deviation = + 8.06 The total disbursement summary from the loan by The World Bank to the end of October 2016 was USD 78,314,016.61 equivalent to approximately 31.33 of the loan funds. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of October 2016. Appendix A shows the Overall Loan Progress Status. Category Description Loan Restructuring Amount US Disbursement This Period Previous Disbursement Totals Disbursed to End October 2016 in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 2,720,412.34 68,803,498.44 71,523,910.78 32.45 2 Part 2 Implementation Support 17,000,000.00 1,206,225.00 5,583,880.83 6,790,105.83 39.94 3 Part 3 Road Sector Institutional Development 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 Original Loan Amount 250,000,000.00 3,926,637.34 74,387,379.27 78,314,016.61 31.33 Breakdown of amount disbursed during the period October 2016 are for Statement of Work Accomplished for the following civil works contract packages : • Package No.15 : IPC Nos. 01 - 03 USD 588,747.08 • Package No.13 : IPC Nos. 04 USD 781,760.62 • Package No.12 : IPC Nos. 06 USD 195,309.92 • Package No.07 : IPC Nos. 02 USD 476,266.80 • Package No.08 : IPC Nos. 04 USD 678,327.92 Replenishment period January September 2016 was amounted USD 1,206,225.00 and the Ending balance for Special Account end of October 2016 USD 1,405,364.88 Include Follow up on BPK audit findings for FY 2014 USD 11,765.00. Western I ndonesia National Roads I mprovement Project 1 - 5

1.3 World Bank Implementation Review Mission and Site Visit

The Technical and Financial Audit Consultant mission bank took place on October 3, 2016 until October 6, 2016 with site visit inspection on Package 17.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement

As of end this reporting month, eighteen 18 out of the nineteen 19 contract packages are already procured and are either completed, under construction and awaiting the issuance of Notice To Proceed NTP to commence the Works. The remaining one 1 package is still under final procurement stages. The current status of Contract Package which is under final procurement stage is:

1. Package No.10 Sp. Empat Sp. Air Balam AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 61.70 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As mentioned in previous reports, the revised Bid Evaluation Report BER has been issued No Objection Letter NOL by the World Bank to award the contract to the joint operation of PT. Lancarjaya Mandiri Abadi and PT. Cahaya Tunggal Abadi in the amount of Rp.424,285,260,782.50 with 720 calendar days time completion. The revised Bid Evaluation Report BER and contract award recommendation is still being thoroughly evaluated by the Ministry before rendering decision whether to accept and confirm POKJA s evaluation report. 1.5 Procurement of Consultancy Package Under Category 2 of the Revised Loan Agreement Reallocation. Technical Assistance for Development of Slope Stabilization, Design and Management The Technical Assistance for Disaster Risk Reduction was canceled based on the results of meeting between DGH and the WB on October 12, 2015. It was decided to cancel the Technical Assistance and replaced by a Technical Assistance for Development of Slope Stabilization, Design and Management under Loan Category- 2. As mentioned in previous Monthly Report, eight 8 interested consultants met the deadline for submission of Expression of Interest . After POKJA s evaluation, six 6 consulting firms made the shortlist, four 4 international and two 2 local companies. The revised shortlisting proposal from POKJA and the revised Request For Proposal RFP have already been submitted to World Bank for request of No Objection Letter NOL. Western I ndonesia National Roads I mprovement Project 2 - 1 2 PROJECT DESCRIPTION

2.1 Background

The Government of Indonesia wishes to continue strengthening of the National Road system in Indonesia while the Eastern Indonesia National Roads Improvement Project EINRIP which is assisted by AusAID through the Australian Indonesia Partnership or AIP, is providing support program of National road and bridge improvement works in Eastern Indonesia. The Western Indonesia National Road Improvement Project WINRIP will provide similar support for National road and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roads administered directly by the National Government, including those currently classified as Provincial, Kabupaten District or non-status roads which are in process of being reclassified as National roads. In addition, provision will be made for major bridge repair works, rehabilitation, duplication and replacement as necessary to complement road betterment works.

2.2 Project Development

The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in the following detail. Key Project Data WINRIP Loan No. 8043-ID Project Cost US350 million Original Loan Amount US250 million Revised Loan Amount NA Board Approval Date 26 May 2011 Loan Signing Date 14 December 2011 Effectiveness Date 12 March 2012 Disbursement as of October 31, 2016 US 78,314,016.61 million 31.33