Civil Works Implementation WINRIP DOC MPR CTC MPR No.46 2016 10 20161031 00435

Western I ndonesia National Roads I mprovement Project 4 - 3

4.4 Civil Works Progress

Activities done during this month on the on-going construction packages were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction, finalization of Field Engineering surveys and mobilization of resources of the newly started contract package. The four 4 contract packages under implementation program AWP-1 were already completed and now under defects liability period for two 2 years since the issuance of TOCs. Under the implementation program AWP-2 and AWP-3, there are currently twelve 12 contract packages that are on-going construction implementation and one 1 package on AWP-3 is already completed. Physical progress of two 2 of the packages are lagging far behind schedule with negative slippages of - 61.59 and -44.34 while progress for the other seven 7 packages are still slightly on or behind schedule and the other three 3 packages are on schedule. Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2. Following are brief status of the on-going construction contract packages : Package No. 1 : Biha Krui The contract package is completed on January 20, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. A more detailed previous status during the whole duration of the contract implementation of this Package is presented in ANNEX P-I Executive Summary Report. Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge The contract package is completed on April 14, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the contract implementation of the Contract Package. Package No. 3 : Manggopoh Padang Sawah The contract package is completed on March 17, 2016 and provisionally handed over to the Employeer on March 17, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. A more detailed status of the project progress during the whole duration of the contract implementation are shown in ANNEX P-3 Executive Summary Report . Package No. 4 : Ipuh Bantal The contract package is completed on May 31, 2016 and provisionally handed over to the Employeer on May 31, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. Shown in ANNEX P-4 Executive Summary Report showing the details and status of the project. Western I ndonesia National Roads I mprovement Project 4 - 4 Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending October 2016 Actual Progress Accomplished Slippage Time Elapsed Remaining Time Remarks AWP-1 1 PT. Jaya Konstruksi Manggala Pratama Tbk Biha - Krui - - - - Completed PHO : Jan 20, 2016 2 PT. Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp.Empat incl.Air Gadang - -- - - Completed PHO : April 14, 2016 3 PT. Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah - - - - Completed PHO : Mar 17, 2016 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal - - - - Completed PHO : May 31, 2016 AWP-2 5 PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha

96.82 35.23

-61.59 92.95 38 CD Based on original contract time and schedule 6 PT. Waskita Karya Tbk Ps. Pedati Kerkap

79.80 74.87

-4.93 87.08 89 CD Based on 2nd revised contract time and schedule 7 PT. Adhi Karya Indrapura - Tapan

24.44 23.49

-0.95 51.83 303 CD Based on original contract time and schedule 8 PT. PPPT. Statika Mitra J.O Bts. Kota Pariaman Manggopoh

13.22 18.79

5.57 34.26

426 CD Based on original contract time and schedule 11 PT. Hutama Karya PT. DMT Mukomuko - Bantal

89.39 74.78

-14.61 85.67 103 CD Based on original contract time and revised schedule 12 PT. LancarjayaPT. Cahaya T.A. JO Kambang Indrapura

2.34 1.97

-2.14 27.43 426 CD Based on original contract time and revised schedule 13 PT. Waskita Karya Persero Tbk Sp. Rukis Tj. Kemuning

63.60 19.25

-44.34 64.95 252 CD Based on original contract time and schedule AWP-3 14 PT. Yasa PT. Conbloc JO Painan Kambang

0.72 2.65

1.92 17.28

426 CD Based on revised contract time and schedule 15 PT. Pembangunan Perumahan Persero Sibolga Bts. Tapsel

30.08 12.04

-18.04 44.82 426 CD Based on revised contract time and schedule 17 PT. Jaya Konstruksi Manggala Pratama Tbk Sp. Gn Kemala Pg. Tampak

39.79 33.32

-6.47 58.83 296 CD Based on original contract time and schedule 19 PT. Rodatekindo Purajaya Lais - Bintunan 100 100 - - - Completed PHO : June 30, 2016 20 PT. Nindya Karya Lubuk Alung Sicincin

0.57 0.63

0.06 12.53

426 CD Based on revised contract time 21 PT. Multi Structure Lubuk Alung Kuraitaji

2.05 1.94

-0.11 12.35 426 CD Based on revised contract time Under defects liability period for 720 calendar days. Western I ndonesia National Roads I mprovement Project 4 - 5 Package No. 5 : Sp. Rampa Poriaha As of end of this period, the actual physical work progress is only 35.23 of the scheduled work progress of 96.82. The delayed works relative to the program schedule farther dropped down to -61.59. Based on the original schedule, barely one 1 month of contract time are left and a huge deficit of still unfinish work of almost 70 to be done which is impossible for the Contractor to finish the remaining works in such short period of time. However, it is anticipated, that the original contract time maybe extended due to pending finalization of the field engineering results and technical justifications. ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap Ps. Pedati Based on the 2 nd revised progress schedule, the actual overall physical work accomplished is 74.87 which is still behind schedule by -4.93. Basically the only remaining major work item to be completed is the asphalt pavement which is 70 component of the whole contract and the end of this period, 44 of the work item is already completed with still 26 to be done. For the Contractor to catch-up with the revised completion date on January 28, 2017, at least a minimum of 8.4 progress must be attained per month during the remaining three 3 months of the revised contract time. ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura Tapan During the month, the Contractor speed up the work as of 6.79 progress had been achieved as compared with 3.83 progress in the preceeding month, however the actual overall progress is still less on schedule by 0.95. Barring any unforeseen circumstances that will interupt or disrupt the execution of the works, the target date of completion on August 30, 2017 can be easily achieved, provided the Contractor shall produce at least minimum 7 progress every month during the remaining contract time of ten 10 months. ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh As the month ended, the overall actual physicalwork progress achieved is 18.79 which is ahead of schedule by +5.57 relative to the progress schedule of 13.22. At the rate the Contractor implement the works, there is no reason that the project cannot be completed on time. Based on simple analysis, at least a monthly progress of 5.5 shall be attained by the Contractor to met the target date of completion on December 31, 2017. ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko Based on the revised schedule due to approval of the results of Field Engineering , the actual overall