Western I ndonesia National Roads I mprovement Project 4 - 23
implementation. •
Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter NOL on November 26, 2015.
• Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL issued by
Bank on March 8, 2016. B. Pending Issues, Concern and Actions
a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared.
b LARAP Implementation is underway for the remaining 18 PAP be allocated 2015 national budget and schedule to be settled on Dec 2015.
c Monitoring Report for the compensation payments of previously paid PAPs still to be prepared for submission to World Bank.
C. Update during this reporting month of October 2016 a Monitoring Report No.3 for compensation payment of 33 PAPs submitted to WB on
October 24, 2016. b Total PAP = 259; Compensated = 259; Percent complete = 100.00.
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak Province
: Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 •
Monitoring Report for 154 of the total 2.014 PAPs was given No Objection Letter NOL on October 13, 2015.
• Monitoring Report for 735 of the remaining 1.860 PAPs was given No Objection Letter NOL on
November 26, 2015. •
A Monitoring Report for the compensation payments progress for 1,156 APs is under submission to WB.
B. Pending Issues, Concern and Actions a Compensation payments for the remaining 260 PAPs is under process.
b DIPA 2016 about 20 billion IDR was ready. A. Update during this reporting month of October 2016
a Total PAP = 1.982; Compensated = 2.041; Percent complete = 88.7.
18. Monitoring Report of the LARAP Package No.18
: Mukomuko Bts. Sumbar Province
: Bengkulu
Cancelled from the WINRIP Program.
19. Monitoring Report of the LARAP Package No.19
: Lais - Bintunan Province
: Bengkulu
B. Previous Status : •
World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation
Western I ndonesia National Roads I mprovement Project 4 - 24
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 for the LARAP
implementation. •
Monitoring Report for 208 of the remaining 272 PAPs was given No Objection Letter NOL on November 26, 2015.
C. Pending Issues, Concern and Actions •
No more issue LARAP fully completed. D. Update during this reporting month of October 2016
a A Monitoring Report for the compensation payments progress for the remaining of 64 APs is under submission to WB
b Total PAP = 538 updated; Compensated = 538; Percent complete = 100.
20. Monitoring Report of the LARAP Package No. 20
: Lubuk Alung - Sicincin Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions
a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of October 2016
a NOL WB of the Monitoring Report of the payments progress for 515 PAP on Sep 26, 2016. b The remaining Aps is under appraisal process
c Total PAP = 892; Compensated =515; Percent complete =76.5.
21. Monitoring Report of the LARAP Package No. 21
: Lubuk Alung - Kuraitaji Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. •
NOL WB of the Monitoring Report-1 for compensation payment of 515 out of the total 1,245 PAPs on August 23, 2016
B. Pending Issues, Concern and Actions a Compensation payments for the remaining of APs is under process
C. Update during this reporting month of October 2016 a No update for reporting of the payment progress for the remaining PAP
b A Monitoring Report of the compensation payments progress for of 605 APs from the remaining of 730 Aps is under preparation by Satker
c Total PAP = 1,245; Compensated = 1,120; Percent complete = 89.9.