Document Library System, used to record all information of document and
Western I ndonesia National Roads I mprovement Project 6 - 2
person 1 due to the bridge development and status of additional LARAP for package 2
19. Send to the Bank final LARAP document of package 5 signed by the
relevant Government authority PMU and CTC
• August 16, 2016
20. Send to the Bank the right of use permission letter for the Forestry
Department for the existing road of package 5 PMU and CTC
• End of August
2016 21.
Carry out remedial actions for the LARAP implementation of package 5
PMU •
As soon as the DIPA revision is
done 22.
Send to the Bank the monitoring report of LARAP implementation of package 5
PMU •
After completion of
remedial actions
23. Submit LARAP monitoring reports for packages 11, 15, 16 and 19 to
the Bank PMU
• End of August
24. Submit LARAP monitoring report for package 7
• Beginning of
September 2016
25. Submit LARAP monitoring reports for package 10, 12, and 14
• Mid-September
2016 26.
Submit LARAP monitoring report for package 8 •
Mid-October 2016
27. Submit LARAP monitoring report for package 13 for 590 APs
PMU •
End of August 28.
Submit LARAP monitoring report for package 21 formally 515 APs PMU
• August 16, 2016
29. Submit LARAP monitoring report for package 20
• PMU and CTC
• End of August
2016 30.
Completely follow up on the FY2015 audit findings and report to the Bank
• •
December 31, 2016
31. Submit the quarterly IFR for April to June 2016 to the Bank
• PMU
• August 15, 2016
32. Provide additional follow-up response to the quality improvement
support inspection reports TFAC for packages 1, 6 and 19 •
PMUDSC •
August 12, 2016 33.
Send the revised TFAC response for package 3 informally to the Bank
• PMUDSC
• August 11, 2016
34. Send the TFAC response formally to the Bank for packages 1, 2, 3, 4,
6, 19 and 11 •
PMUDSC •
September 2, 2016
35. Put the Mid-term review report on WINRIP website
• PMUCTC
• August 20, 2016
36. Submit to the Bank the 2015IRMS traffic data for the 19 road
packages •
PMUCTC •
September 15, 2016
37. Regularly submit the quarterly progress reports to the Bank
• PMU
• Noted for each
calendar quarter
38. Disclose updated procurement plan after Bank approval in the
Winrip website linked to MPW Website •
PMU •
After Bank approval
39. Update the newsletter quarterly, including the list of contracts,
implementation progress, project related workshops and number, typology and status of complaints
• PMU
• Every quarter
40. Send quarterly newsletter to the civil society forum in each project
province in hard copy or through an electronic mailing system •
PMU •
Every quarter
Western I ndonesia National Roads I mprovement Project 6 - 3