commit to user 323
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Total 171,695.70
8.B 1 M2 LANTAI KERAMIK UKURAN 20 × 20 cm
Pekerja oh
0.700 28,000.00
19,600.00 Tukang batu
oh 0.350
39,600.00 13,860.00
Kepala tukang oh
0.035 48,400.00
1,694.00 Mandor
oh 0.035
49,500.00 1,732.50
Ubin keramik bh
26.500 3,680.00
97,520.00 Portland Cement PC
kg 10.400
1,178.75 12,259.00
Pasir pasang m³
0.045 129,375.00
5,821.88 Semen warna
kg 1.620
1,750.00 2,835.00
Jumlah 118,435.88
36,886.50 155,322.38
Jasa konstruksi 10 15,532.24
Total 170,854.61
8.C 1 M2 DINDING KERAMIK UKURAN 20 × 20 cm
Pekerja oh
0.900 28,000.00
25,200.00 Tukang batu
oh 0.450
39,600.00 17,820.00
Kepala tukang oh
0.045 48,400.00
2,178.00 Mandor
oh 0.045
49,500.00 2,227.50
Ubin keramik bh
26.500 3,680.00
97,520.00 Portland Cement PC
kg 9.300
1,178.75 10,962.38
Pasir pasang m³
0.018 129,375.00
2,328.75 Semen warna
kg 1.940
1,750.00 3,395.00
Jumlah 114,206.13
47,425.50 161,631.63
Jasa konstruksi 10 16,163.16
Total 177,794.79
9. PEKERJAAN SANITASI
9.A 1 BUAH PASANG KLOSET JONGKOK PORSELIN
Pekerja oh
1.000 28,000.00
28,000.00 Tukang batu
oh 1.500
39,600.00 59,400.00
Kepala tukang oh
1.500 48,400.00
72,600.00 Mandor
oh 0.160
49,500.00 7,920.00
Kloset jongkok bh
1.000 178,250.00
178,250.00 Portland Cement PC
kg 6.000
1,178.75 7,072.50
commit to user 324
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Pasir pasang m³
0.010 129,375.00
1,293.75 Jumlah
186,616.25 167,920.00
354,536.25 Jasa konstruksi 10
35,453.63 Total
389,989.88 9.B
1 BUAH PASANG BAK MANDI FIBER GLASS
Pekerja oh
1.800 28,000.00
50,400.00 Tukang batu
oh 2.700
39,600.00 106,920.00
Kepala tukang oh
0.540 48,400.00
26,136.00 Mandor
oh 0.110
49,500.00 5,445.00
Bak fiberglass bh
1.000 207,000.00
207,000.00 Perlengkapan
0.180 207,000.00
37,260.00 Jumlah
244,260.00 188,901.00
433,161.00 Jasa konstruksi 10
43,316.10 Total
476,477.10 9.C
1 BUAH PASANG WESTAFEL
Pekerja oh
1.200 28,000.00
33,600.00 Tukang batu
oh 1.450
39,600.00 57,420.00
Kepala tukang oh
0.150 48,400.00
7,260.00 Mandor
oh 0.100
49,500.00 4,950.00
Westafel bh
1.000 316,250.00
316,250.00 Perlengkapan
0.120 316,250.00
37,950.00 Portland Cement PC
kg 6.000
1,178.75 7,072.50
Pasir pasang m³
0.010 129,375.00
1,293.75 Jumlah
362,566.25 103,230.00
465,796.25 Jasa konstruksi 10
46,579.63 Total
512,375.88 9.D
1 BUAH PASANG FLOORDRAIN
Pekerja oh
0.010 28,000.00
280.00 Tukang batu
oh 0.100
39,600.00 3,960.00
Kepala tukang oh
0.010 48,400.00
484.00 Mandor
oh 0.005
49,500.00 247.50
Floordrain bh
1.000 34,500.00
34,500.00 Jumlah
34,500.00 4,971.50
39,471.50 Jasa konstruksi 10
3,947.15
commit to user 325
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Total 43,418.65
9.E 1 BUAH PASANG KRAN DIAMETER 34 ATAU 12
Pekerja oh
0.010 28,000.00
280.00 Tukang batu
oh 0.100
39,600.00 3,960.00
Kepala tukang oh
0.010 48,400.00
484.00 Mandor
oh 0.005
49,500.00 247.50
Floordrain bh
1.000 34,500.00
34,500.00 Seal tape
bh 0.025
1,725.00 43.13
Jumlah 34,543.13
4,971.50 39,514.63
Jasa konstruksi 10 3,951.46
Total 43,466.09
10. PEKERJAAN INSTALASI AIR