commit to user 321
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Mandor oh
0.120 49,500.00
5,940.00 Balok kayu bankirai
m³ 1.100
9,430,000.00 10,373,000.00 Paku 5 cm - 12 cm
kg 3.000
13,800.00 41,400.00
Besi strip tebal 5 mm kg
15.000 9,900.00
148,500.00 Jumlah
10,562,900.00 401,028.00
10,963,928.00 Jasa konstruksi 10
1,096,392.80 Total
12,060,320.80 6.F
1M PASANG NOK GENTENG BETON
Pekerja oh
0.400 28,000.00
11,200.00 Tukang kayu
oh 0.200
40,700.00 8,140.00
Kepala tukang oh
0.020 48,400.00
968.00 Mandor
oh 0.002
49,500.00 99.00
Nok genteng beton bh
3.500 4,600.00
16,100.00 Paku payung
kg 0.050
11,500.00 575.00
Portland Cement PC kg
10.800 1,178.75
12,730.50 Pasir pasang
m³ 0.032
129,375.00 4,140.00
Semen warna kg
1.000 1,750.00
1,750.00 Jumlah
35,295.50 20,407.00
55,702.50 Jasa konstruksi 10
5,570.25 Total
61,272.75 6.G
1 M PASANG LISPLANK 3 × 20 cm, KAYU KAMFER
Pekerja oh
0.100 28,000.00
2,800.00 Tukang kayu
oh 0.200
40,700.00 8,140.00
Kepala tukang oh
0.020 48,400.00
968.00 Mandor
oh 0.005
49,500.00 247.50
Kayu kamfer papan m³
0.007 9,545,000.00
66,815.00 Paku biasa 2-5
kg 0.050
11,500.00 575.00
Jumlah 67,390.00
12,155.50 79,545.50
Jasa konstruksi 10 7,954.55
Total 87,500.05
7. PEKERJAAN PLAFOND
7.A 1 M2 PASANG PLAFOND AKUSTIK 60 × 120 cm + RANGKA ALUMUNIUM
Pekerja oh
0.500 28,000.00
14,000.00
commit to user 322
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Tukang besi oh
0.500 40,700.00
20,350.00 Kepala tukang
oh 0.050
48,400.00 2,420.00
Mandor oh
0.025 49,500.00
1,237.50 Profil alumunium
m 3.600
48,300.00 173,880.00
Kawat dia. 4 mm kg
0.150 14,950.00
2,242.50 Ramset
bh 1.050
2,875.00 3,018.75
Akustik 60 × 120 cm lbr
1.500 25,300.00
37,950.00 Jumlah
217,091.25 38,007.50
255,098.75 Jasa konstruksi 10
25,509.88 Total
280,608.63 7.B
1 M2 PASANG PLAFOND GYPSUM BOARD + RANGKA HOLLOW ALUMUNIUM
Pekerja oh
0.500 28,000.00
14,000.00 Tukang besi
oh 0.500
40,700.00 20,350.00
Kepala tukang oh
0.050 48,400.00
2,420.00 Mandor
oh 0.025
49,500.00 1,237.50
Hollow alumunium m
0.800 36,400.00
29,120.00 Paku skrup
bh 9.000
280.00 2,520.00
Ramset bh
1.000 2,875.00
2,875.00 Gypsum board
lbr 1.000
60,950.00 60,950.00
Jumlah 95,465.00
38,007.50 133,472.50
Jasa konstruksi 10 13,347.25
Total 146,819.75
8. PEKERJAAN PENUTUP LANTAI DAN DINDING
8.A 1 M2 LANTAI KERAMIK UKURAN 30 × 30 cm
Pekerja oh
0.700 28,000.00
19,600.00 Tukang batu
oh 0.350
39,600.00 13,860.00
Kepala tukang oh
0.035 48,400.00
1,694.00 Mandor
oh 0.035
49,500.00 1,732.50
Ubin keramik bh
11.870 8,337.50
98,966.13 Portland Cement PC
kg 10.000
1,178.75 11,787.50
Pasir pasang m³
0.045 129,375.00
5,821.88 Semen warna
kg 1.500
1,750.00 2,625.00
Jumlah 119,200.50
36,886.50 156,087.00
Jasa konstruksi 10 15,608.70
commit to user 323
Tugas Akhir
Perencanaan Struktur Gedung Sekolah 2 Lantai RAB
BAB 9 RENCANA ANGGARAN BIAYA NO
MACAM PEKERJAAN
MACAM BAHAN SATUAN
KOEFISIEN HARGA
SATUAN Rp
JUMLAH HARGA
BAHAN Rp
JUMLAH HARGA
UPAH Rp
TOTAL Rp
Total 171,695.70
8.B 1 M2 LANTAI KERAMIK UKURAN 20 × 20 cm
Pekerja oh
0.700 28,000.00
19,600.00 Tukang batu
oh 0.350
39,600.00 13,860.00
Kepala tukang oh
0.035 48,400.00
1,694.00 Mandor
oh 0.035
49,500.00 1,732.50
Ubin keramik bh
26.500 3,680.00
97,520.00 Portland Cement PC
kg 10.400
1,178.75 12,259.00
Pasir pasang m³
0.045 129,375.00
5,821.88 Semen warna
kg 1.620
1,750.00 2,835.00
Jumlah 118,435.88
36,886.50 155,322.38
Jasa konstruksi 10 15,532.24
Total 170,854.61
8.C 1 M2 DINDING KERAMIK UKURAN 20 × 20 cm
Pekerja oh
0.900 28,000.00
25,200.00 Tukang batu
oh 0.450
39,600.00 17,820.00
Kepala tukang oh
0.045 48,400.00
2,178.00 Mandor
oh 0.045
49,500.00 2,227.50
Ubin keramik bh
26.500 3,680.00
97,520.00 Portland Cement PC
kg 9.300
1,178.75 10,962.38
Pasir pasang m³
0.018 129,375.00
2,328.75 Semen warna
kg 1.940
1,750.00 3,395.00
Jumlah 114,206.13
47,425.50 161,631.63
Jasa konstruksi 10 16,163.16
Total 177,794.79
9. PEKERJAAN SANITASI