Beban Mati Perencanaan Kuda-Kuda Utama B

commit to user 69 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

3.6.3. Perhitungan Pembebanan Kuda-Kuda Utama B

Data pembebanan : Berat gording = 11 kgm Berat penutup atap = 50 kgm 2 Berat penggantung dan plafond = 18 kgm 2 Beban hujan = 40 – 0,8α kgm 2 = 40 – 0,8 × 35 = 12 kgm 2 Gambar 3.22. Pembebanan Kuda-Kuda Utama B Akibat Beban Mati

3.6.3.1. Perhitungan Beban

1. Beban Mati

a. Beban P 1 = P 9 1. Beban gording = berat profil gording × panjang gording is = 11 × 4,5 = 49,5 kg 2. Beban atap = luas atap hrtj × berat atap = 9,114 × 50 = 455,7 kg commit to user 70 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

3. Beban plat sambung = 30 × beban kuda-kuda = 30 × 9,38 = 2,814 kg 4. Beban bracing = 10 × beban kuda-kuda = 10 × 9,38 = 0,938 kg 5. Beban plafond = luas plafond hrtj × berat plafond = 7,465 × 18 = 134,37 kg b. Beban P 2 = P 8 1. Beban gording = berat profil gording × panjang gording gq = 11 × 3,875 = 42,625 kg 2. Beban atap = luas atap fprh × berat atap = 5,914 × 50 = 295,7 kg 3. Beban plat sambung = 30 × beban kuda-kuda = 30 × 18,43 = 5,529 kg 4. Beban bracing = 10 × beban kuda-kuda = 10 × 18,43 = 1,843 kg c. Beban P 3 = P 7 1. Beban gording = berat profil gording × panjang gording eo = 11 × 3,25 = 35,75 kg 2. Beban atap = luas atap dnpf × berat atap = 4,960 × 50 = 248 kg commit to user 71 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

3. Beban plat sambung = 30 × beban kuda-kuda = 30 × 23,51 = 7,053 kg 4. Beban bracing = 10 × beban kuda-kuda = 10 × 23,51 = 2,351 kg d. Beban P 4 = P 6 1. Beban gording = berat profil gording × panjang gording cm = 11 × 2,625 = 28,875 kg 2. Beban atap = luas atap blnd × berat atap = 4,007 × 50 = 200,35 kg 3. Beban plat sambung = 30 × beban kuda-kuda = 30 × 29,02 = 8,706 kg 4. Beban bracing = 10 × beban kuda-kuda = 10 × 29,02 = 2,902 kg e. Beban P 5 1. Beban atap = luas atap aklb × berat atap = 1,645 × 50 = 82,25 kg 2. Beban plat sambung = 30 × beban kuda-kuda = 30 × 22,15 = 6,645 kg 3. Beban bracing = 10 × beban kuda-kuda = 10 × 22,15 = 2,215 kg commit to user 72 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

4. Beban reaksi = 2 × reaksi jurai + reaksi setengah kuda-kuda = 2 × 179,40 + 721,91 = 1080,71 kg f. Beban P 10 = P 16 1. Beban plafond = luas plafond fprh × berat plafond = 4,844 × 18 = 87,192 kg 2. Beban plat sambung = 30 × beban kuda-kuda = 30 × 11,41 = 3,423 kg 3. Beban bracing = 10 × beban kuda-kuda = 10 × 11,41 = 1,141 kg g. Beban P 11 = P 15 1. Beban plafond = luas plafond dnpf × berat plafond = 4,063 × 18 = 73,134 kg 2. Beban plat sambung = 30 × beban kuda-kuda = 30 × 19,53 = 5,859 kg 3. Beban bracing = 10 × beban kuda-kuda = 10 × 19,53 = 1,953 kg h. Beban P 12 = P 14 1. Beban plafond = luas plafond blnd × berat plafond = 3,282 × 18 = 59,076 kg 2. Beban plat sambung = 30 × beban kuda-kuda = 30 × 24,6 = 7,38 kg commit to user 73 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

3. Beban bracing = 10 × beban kuda-kuda = 10 × 24,6 = 2,46 kg i. Beban P 13 1. Beban plafond = luas plafond aklb × berat plafond = 1,348 × 18 = 24,264 kg 2. Beban plat sambung = 30 × beban kuda-kuda = 30 × 39,94 = 11,982 kg 3. Beban bracing = 10 × beban kuda-kuda = 10 × 39,94 = 3,994 kg Tabel 3.20. Rekapitulasi Beban Mati Kuda-Kuda Utama B Beban Beban Gording kg Beban Atap kg Beban Plat Sambung kg Beban Bracing kg Beban Plafond kg Beban Reaksi kg Jumlah Beban kg Input SAP kg P 1 = P 9 49,5 455,7 2,814 0,938 134,37 --- 643,32 644 P 2 = P 8 42,625 295,7 5,529 1,843 --- --- 345,7 346 P 3 = P 7 35,75 248 7,053 2,351 --- --- 293,15 294 P 4 = P 6 28,875 200,35 8,706 2,902 --- --- 240,83 241 P 5 --- 82,25 6,645 2,215 --- 1080,71 1171,82 1172 P 10 = P 16 --- --- 3,423 1,141 87,192 --- 91,76 92 P 11 = P 15 --- --- 5,859 1,953 73,134 --- 80,95 81 P 12 = P 14 --- --- 7,38 2,46 59,076 --- 68,92 69 P 13 --- --- 11,982 3,994 24,264 --- 40,24 41 commit to user 74 Tugas Akhir Perencanaan Struktur Gedung Sekolah 2 Lantai RAB

BAB 3 PERENCANAAN ATAP

2. Beban Hidup