CTC Manning CTC Consultants .1

Western I ndonesia National Roads I mprovement Project 12 Position MM Name Assignment Time Used to End of February 2013 Contract Time Remaining Start End Bridge Engineer 5 Harimurti Suprihartono Jan-2013 May-2013 1.93 3.07 Quality Assurance Engineer 36 Uray Abdul Manaf - - - 36.00 Financial Management Specialist 36 Uus Martawijaya Nov-2012 Oct-2015 3.37 32.63 Environmental Specialist 30 Leti Hermawati Dec-2012 Jun-2015 2.43 27.57 Social Impact Specialist 36 M. Sutopo Nov-2012 Oct-2015 3.37 32.63 Procurement Specialist-1 12 Darmansiri - - - 12.00 Procurement Specialist-2 12 Rudi Rungkat Nov-2012 Mar-2013 3.37 8.63 Management Information Specialist 30 Agung Lukito - - - 30.00 Community Development Officer 36 Yakobus Jan-2013 Dec-2015 1.90 34.10 Notes: : Not yet mobilized The table shows that a number of key personnel have not yet been mobilized even though the project has already been running for almost five months. A number of the originally proposed names are no longer available due to a late start for the project and substitutes have been proposed but the project is still awaiting approval for these proposed replacement key personnel. These personnel are critically required for the production of reports in a timely fashion. Since the original Team Leader was resigned prior to his mobilization, the CTC proposed a replacement for the Team Leader position to DGH. The qualification of the replacement has been being reviewed by DGH. The DSC has not been established yet. In parallel with the instruction to speed up the process, detailed engineering design DED of some subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. The CTC has been instructed by DGH for acting as DSC to review the DEDs completed by the P2JNs.

3.1.3 CTC Contract

The CTC contract for “Western Indonesia National Roads Improvement Project” Contract No. 06-20CTCTALN80431112 was signed on 05 November 2012. The contract is between the Government of Indonesia represented by the Ministry of Public Works, Directorate General of Highways and PT. Perentjana Djaya in joint venture with Yongma Engineering Co.Ltd. and PT. Epadascon Permata Engineering Consultant. The notice to proceed was issued by letter dated 6 November 2012 from the PPK, Western I ndonesia National Roads I mprovement Project 13 and the official starting date of the contract was set at 6 November 2012. The following table shows a list of contract amendment for the CTC contract with DGH. Contract Date USD Excl. VAT IDR Excl. VAT Original Contract 5-Nov-2012 1,276,700 21,415,400,000

3.2 DSC Consultants

A Design and Supervision Consultant DSC will be responsible for design of WP-2 and WP-3 civil works and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the BinaMarga Regional Office Balai II, and will be based in Padang, West Sumatra. 4 CIVIL WORKS

4.1 Detailed Design Preparation

Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed for all projects proposed for WP-1. WP-2 nine subprojects and WP-3 eight subprojects will be designed by DSC and the construction supervision of all the works programs will be performed by the DSC. During the CTC mobilization, the DSC has not been established yet. In parallel with the instruction to speed up the process, detailed engineering design DED of some subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. Senior Highway Engineer is mobilized on schedule on 1 February. Senior Highway Engineer has implemented Technical Design Review with Highway Engineer for Package No.5 Sp. Rampa – Poriaha. Simultaneously, Senior Highway Engineer have prepared the technical parts in the Project Management Manual for WINRIP project which reflected Indonesia BINA MARGA manual and International design manual in order to review the technical design review exactly than other things. The Technical Review and Road Safety Review Report have been included the checklists of Road Engineering and Road Safety audit each package by Senior Highway Engineer and Senior Road Safety Auditor. Progress of Technical Design Reviewing up to the end of February 2013 is included as Appendix B.