Management Information Systems Quality Assurance Current Situation Action Required

Western I ndonesia National Roads I mprovement Project 40 Package supervision comes under the responsibilities of the immediate supervision teams and the relevant DSC but the Quality Assurance Engineer from CTC, when mobilized, will periodically monitor their performance. Western I ndonesia National Roads I mprovement Project 41 7 ISSUES and RECOMMENDATIONS

7.1 Current Situation

The main issue during February 2013 is the procurement of four 4 packages under AWP-1. The AERs have been discussed between the DGH and the Bank for more than a half year. The tender could not be started until the AERs are approved by the Bank even the Bidding Documents are ready to be issued. In the meeting held on 13 February 2013 and attended by respective representative of the Bank, DGH, PMU, CTC and Balai, it was noted that the delay factor is related to the quality of the Procurement Committee. At the other side, the existing road conditions of the four packages under AWP-1, which are predicted being deteriorated rapidly by the traffic during almost a year, shall be anticipated. Another issue is establishment of the Design and Supervision Consultant DSC. It is required to expedite the DSC recruitment process. The DEDs for AWP-2 and AWP-3 packages shall be completed soon and the procurement can be started immediately.

7.2 Action Required

In order to speed up the procurement process and reduce delays, a Workshop for Bid Documents Evaluation of four packages under AWP-1 was being delivered from 28 February to 1 March 2013, in Swiss-Bell Hotel at Kemang Raya No. 7 Jakarta Selatan. The workshop was attended by 33 participants from Procurement Committee Pokja, SatkerPPK, Balai II, Balai III, and PMU. The project managers PPKs are suggested and required to update the DEDs of the AWP-1 packages following actual condition of the existing roads. The estimated construction cost should be considered to not significantly increase. Otherwise, the prequalification shall be cancelled since the experience criteria for the Applicants were set based on previous estimated construction cost. The proposed consultants rank based on the Technical Evaluation Report has been submitted by DGH on 20 December 2012. The Bank has no objection on the report as stated in Bank’s letter dated 21 February 2013. The opening of Financial Proposal will be conducted by the DGH’s Procurement Committee in short coming period. Western Indonesia National Roads Improvement Project Appendix A Overall Loan Progress Exchange Rate : 1 equal to IDR 9,750 28 February 2013 Estimated Contractors or Total Est. Budget Starting Completion Consultants Man-Month WB + GOI Remarks Date Date Name Excl. the PIP Original Revised Physical Man-Month Physical Man-Month Physical Man-Month Supp. Staff USD, Excl.VAT Excl. VAT Excl. VAT MM MM MM 1 Betterment and Capacity 314,900,000.00 Expansion of National Roads 1.A AWP-1 ICB DGH 81,630,000.00 Procurement process prequalification. 1.B AWP-2 and AWP-3 ICB NCB DGH 227,100,000.00 Detailed Engineering Design preparation. 1.C Contingency - DGH 6,170,000.00 2 Implementation Support 6,000,000.00 2.A Core Team Consultants CTC QCBS DGH 6-Nov-12 15-Feb-16 PT. Perentjana Djaja 556 5,000,000.00 1,276,700.00 9.849

54.76 6.432

35.76 -3.417

-19.00 Ongoing Joint Venture with Rp21,415,400,000.00 Yongma Engineering Co.Ltd. Or US equivalent total : PT. Epadascon Permata 3,473,151.28 2.B Design Superv. Consultants QCBS DGH Recruitment process. 2.C Incremental Operating Cost Varies PMU 1,000,000.00 Including Technical Audits 3 Road Sector Institutional 1,000,000.00 Development 3.A Capacity Building for NCB DGH 350,000.00 Preparation of TOR. Disaster Risks Reduction 3.B Capacity Building for NCB DGH 350,000.00 Preparation of TOR. Environmental Management 3.C Capacity Building for NCB DGH 300,000.00 Preparation of TOR. Road Safety 4 Contingency for Disaster - DGH - Risk Response 5 Unallocated - DGH 18,100,000.00 Total 340,000,000.00 3,473,151.28 9.849

54.76 6.432

35.76 -3.417

-19.00 PROGRESS Respon- sibility Contract ValueBudget Total WB + GOI Appendix - A OVERALL PROGRESS STATUS Description WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WINRIP IBRD LOAN No. 8043-ID Proc. Method Category Planned Actual Balance CTC 30-Nov-12 31-Dec-12 31-Jan-13 28-Feb-13 31-Mar-13 30-Apr-13 31-May-13 30-Jun-13 31-Jul-13 31-Aug-13 30-Sep-13 31-Oct-13 30-Nov-13 Team Leader 25-Mar-13 0.25 1.25 2.25 3.25 4.25 5.25 6.25 7.25 8.25 Senior Highway 1-Feb-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Senior Proc Senior Road Sft 1-May-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 Ass. TL 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Highway Eng 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Qualty Ass. Eng 1-Jul-13 1.00 2.00 2.82 3.82 4.82 Financial 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Enviro 17-Dec-12 0.45 1.45 2.45 3.45 4.45 5.45 6.45 7.45 8.45 9.27 10.27 11.27 Socio 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Proc. Speclt-1 Proc. Speclt-2 19-Nov-12 0.33 1.33 2.33 3.33 4.35 5.35 6.35 7.35 8.35 9.35 10.35 11.35 12.35 MIS 1-May-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 Comm.Devlp. 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 Total Prof 1.65

7.10 14.10

22.10 30.37

39.37 50.36

61.36 73.36

85.36 97.00

109.00 121.00 Ass. Highway Ass. Financial 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Ass. EnvSocio 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33 Ass. MIS 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 Ass. Comm. Dev 1-Feb-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Ass. Proc-1 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 Ass. Proc-2 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 Total Sub Prof 0.66

2.66 7.66

13.66 19.66

25.66 31.66

37.66 43.66

49.66 55.66

61.66 67.66

Grand Total 2.31

9.76 21.76

35.76 50.03

65.03 82.02

99.02 117.02

135.02 152.66 170.66 188.66 Mobilized Total Manmonth Up To