Western I ndonesia National Roads I mprovement Project 39
the type of land asset affected by project, to carry out interview with PAPs, to get information related land acquisition process and to check the current status of the
Appraisal Team readiness for payment of the land acquisition.
6.7 Management Information Systems
The Information Management Specialist has not yet been mobilized. The activity for management information system will be reported soon after his mobilization.
6.8 Quality Assurance
The Quality Assurance Engineer has not yet been mobilized. The activity for project quality assurance will be reported soon after his mobilization.
6.9 Project Risks and Mitigation Measures 6.9.1
Risks Related to Delays
Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the
procurement of AWP-2 and AWP-3 sub-projects. As discussed previously above, the DED of several subprojects of WP-2 and WP-3 were prepared and completed
by respective P2JN. The CTC has then been instructed by DGH to review the DEDs of some packages completed by the P2JNs and the Senior Highway
Engineer has implemented Technical Design Review with the Highway Engineer for Package No.5 : Simpang Rampa – Poriaha.
6.9.2 Financial Risks
The following factors will be monitored during implementation of the loan project. •
Loan Amount •
Actual Tender Prices •
Price Adjustment •
Currency Fluctuation •
Current Estimated Situation No risk was detected until preparation of this report since the main program of the
loan civil works implementation has not yet been started with contract sign.
6.9.3 Risks Related to Quality
The quality of work is inherently tied to the competence of the Contractors and the diligence of the Supervision Teams. The competence or otherwise of
contractors shall be considered at the time of bid evaluation and prior to the award of any contract.
The quality of supervision however is influenced by the following factors: •
Ensuring that supervision staff levels are fully manned with competent, honest, qualified and experienced personnel.
• The provision of properly equipped laboratories with properly trained
operators for each package.