mil 20.06 WINRIP ACTUAL PROGRESS UP TO FEBRUARY 2016 AND FORECAST UP TO DECEMBER 2017

Western I ndonesia National Roads I mprovement Project 1 - 6

3. Package No.12 Kambang - Indrapura AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 55.20 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As previously mentioned in the preceeding report, Contract Agreement has been executed on January 28, 2016 between the Government of Indonesia GOI and the winning responsive bidder, PT. Lancarjaya Mandiri Abadi PT. Cahaya Tunggal Abadi JO for a contract amount of Rp. 358,650,400,000 and 720 calendar days contract time. Copy of the signed contract is still in process for submission to World Bank for request issuance of Form 384 for disbursement purpose.

4. Package No.16 Seblat-Ipuh AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 34.50 kilometers and is located in the Province of Bengkulu. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System. Bid Evaluation Report BER has been completed by POKJA and submitted to World Bank on January 11, 2016 for review and issuance of No Objection Letter NOL. However, per Bank s letter of January 20, 2016 regarding results of their prior review of the BER have comments on the proposed disqualification of five 5 lower priced bidders. In line with the Bank s comments a revised Bid Evaluation Report is still under preparation for resubmission to World Bank for review and issuance of no objection to award the contract.

5. Package No.14 Painan - Kambang AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled, the submission and opening of bids took place in Padang on January 5, 2016. There were four 4 applicant bidders 3 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the four 4 bidders with their respective bid prices : • PT. Yasa Patria Perkasa Conbloc, JO Rp. 214,602,400,000 • PT. Waskita Karya Rp. 239,449,604,000 • PT. Jaya Konstruksi Rp. 239,628,825,000 • PT. PP Rp. 249,277,000,000 The lowest canvassed bid is submitted by the joint venture operation of PT. Yasa Patria Perkasa and Conbloc with an amount of Rp. 214,602,400,000 which is 19.80 Western I ndonesia National Roads I mprovement Project 1 - 7 below the approved Owner s Estimate OE of Rp. 267,590,800,000 while the 2 nd lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized upon receipt of responses from the bidders regarding POKJA s letter of request for clarification of some issue from the bidders.

6. Package No.20 Lubuk Alung - Sicincin AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled, the submission and opening of bids took place in Padang on January 5, 2016. There were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the five 5 bidders with their respective bid prices : • PT. Nindya Karya Rp. 113,818,300,000 • PT. Conbloc Infratechno Statika, KSO Rp. 118,172,039,000 • PT. Waskita Karya Rp. 122,767,255,000 • PT. Jaya Konstruksi Rp. 126,670,765,000 • PT. PP Rp. 125,192,900,000 The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of Rp. 113,818,300,000 which is 13.32 below the approved Owner s Estimate OE of Rp. 131,302,200,000 while the 2 nd lowest bid is quoted by PT. PT. Conbloc Infratechno Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00 lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized upon receipt of responses from the bidders regarding POKJA s letter of request for clarification from the bidders.

7. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled the submission and opening of bids took place in Padang on January 5, 2016. There were eight 8 applicant bidders 7 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the eight 8 bidders with their respective bid prices : • PT. Multi Structure Rp. 126,301,991,200