Monitoring Report of the LARAP Package No. 11

Western I ndonesia National Roads I mprovement Project 4 - 20 a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared. b LARAP Implementation is underway for the remaining 18 PAP be allocated 2015 national budget and schedule to be settled on Dec 2015. c Monitoring Report for the compensation payments of previously paid PAPs still to be prepared for submission to World Bank. C. Update during this reporting month of February 2016 a Data of the payments to the 18 PAP Balance from 259 PAPs are under preparation by Satker PJN I Bengkulu. b Updated LARAP documents submitted on February 22, 2016 to World Bank.

17. Monitoring Report of the LARAP Package No.17

: Sp. Gunung Kemala Pg. Tampak Province : Lampung A. Previous Status : • World Bank approved the corrected LARAP documents on November 12, 2013 • Monitoring report for 154 of the total 2.273 PAPs was given No Objection Letter NOL on October 13, 2015. • Monitoring report for 735 of the remaining 2.119 PAPs was given No Objection Letter NOL on November 26, 2015 B. Pending Issues, Concern and Actions a Monitoring Report for the compensation payments for the remaining 1.384 PAPs has to be submitted to World Bank. C. Update during this reporting month of February 2016 a Compensation payments for the remaining 1.384 from 2.273 PAP have been already released. b PMUCTC waiting data of payment progress for the remaining of 1.384 PAPs from Satker PJN II Lampung.

18. Monitoring Report of the LARAP Package No.18

: Mukomuko Bts. Sumbar Province : Bengkulu Cancelled from the WINRIP Program.

19. Monitoring Report of the LARAP Package No.19

: Lais - Bintunan Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation • World Bank issued No Objection Letter NOL on Monitoring Report No.1 for the LARAP implementation. • Monitoring report for 208 of the remaining 290 PAPs was given No Objection Letter NOL on November 26, 2015.