Current Implementation Situation Civil Works

Western I ndonesia National Roads I mprovement Project 1 - 3 Length Ction Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 1 Krui - Biha 25,00 21 mth 8 Jan14 2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan14 3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan14 4 Ipuh - Bantal 42,40 24 mth 10 Jan14 5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun15 11 Feb17 11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb15 11 Feb17 13 SP RUKIS - TJ KEMUNING 56,30 24 mth 11 Feb17 17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep15 23 Agt17 6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar15 02 Jun16 19 LAIS - BINTUNAN 11,60 10 mth 11 Mar15 CONST RUCT ION 300+125 days 08 May16 15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov15 06 Feb18 7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec15 30 Agt17 8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth 10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth 12 KAMBANG - INDRAPURA 55,20 24 mth 14 PAINAN KAMBANG 31,50 21 mth 16 SEBLAT IPUH 34,50 21 mth 20 LUBUK ALUNG SICINCIN 14,60 18 mth 21 LUBUK ALUNG KURAITAJI 16,80 18 mth 9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIPs work program 18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIPs work program Original target : 715,60 km ENVIRONMENT SOCIAL SAFEGUARD Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study Road Safety Owners Estimate Appraisal Public Consultation Procurement Sign Contr Bid Document LARAP Implementation Preparation for Commencement of Work Standard Biding Document PQ ICB ICB ICB ICB ICB 10-Jan-16 CONST RUCT ION 640 + 93 days 19-Apr-16 20-Mar-16 08-Apr-16 CONST RUCT ION 540 days Pack PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018 CONSTRUCTION Review DED RS PQ PROC Review DED RS PQ DED SBD OE + BD DED DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED Review DED RS CONSTRUCTION CONST RUCT ION 450 days SBD OE + BD CONST RUCT ION 720 days CONST RUCT ION 720 days PROC PQ RS Proc COW SBD CONST RUCT ION 730 + 105 days CONST RUCT ION 730 + 75 days CONST RUCT ION 730 + 90 days DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED OE BD Review DED RS PROC PROC PROC Review DED RS PQ Rev-DED RS PROC CONST RUCT ION 720 days ICB ICB ICB ICB NCB NCB NCB Review DED RS Review DED RS SBD OE + BD CONST RUCT ION 810 days CONST RUCT ION 630 days 22-Jul-15 COW CONSTRUCTION Rev-DED RS Rev-DED RS Rev-DED RS ICB ICB ICB NCB NCB NCB NCB COW PROC COW PROC PROC PROC PROC CONSTRUCTION CONSTRUCTION CONSTRUCTION DED CONSTRUCTION Actual Implementation Timeline of WINRIP Western I ndonesia National Roads I mprovement Project 1 - 4

1.2 Disbursement

Loan Allocation and Percent Disbursement To Date REF 1.25 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 Month C o m pl e te Actual Expenditure USD

50.14 mil 20.06 WINRIP ACTUAL PROGRESS UP TO FEBRUARY 2016 AND FORECAST UP TO DECEMBER 2017

ACTUAL February 2016 Forecast February 2016 Forecast Expenditure USD 144.13 mil 57.65 Deviation = 37.59 The total disbursements summary from the loan by World Bank to the end of February 2016 was USD 50,144,535.90 equivalent to approximately 20.06 of the loan funds. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of February 2016. Appendix A shows the Overall Loan Progress Status. Category Description Loan Restructuring Amount US Disbursement This Period Previous Disbursement Totals Disbursed to End February 2016 in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 44,560,655.07 44,560,655.07 20.22 2 Part 2 Implementation Support 17,000,000.00 1,299,000.00 4,284,880.83 5,583,880.83 32.85 3 Part 3 Road Sector Institutional Development 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 Original Loan Amount 250,000,000.00 1,299,000.00 48,845,535.90 50,144,535.90 20.06 The amount disbursed by World Bank during this month of February 2016, replenishment for Special Account period October December 2015 amounting to USD 1,299,000.00. The Ending balance for Special Account to cover the expenditure for Category 2 Part 2 at the end of February 2016 is USD 1,368,582.70. Western I ndonesia National Roads I mprovement Project 1 - 5

1.3 World Bank Implementation Review Mission and Site Visit

During the period February 2016 there was no implementation review mission nor site visit as well as the regular monthly meeting to review the implementation progress and monitoring the key activities on the Agreed Key Action Plans was not held during the period. However, the Technical and Financial Audit Consultant TFAC mission is scheduled to perform and conduct site audits on Package 11 Bantal Mukomuko and Package 19 Lais Bintunan during the period from February 29, 2016 to March 4, 2016.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement

The current status of Contract Packages which are under final procurement stage are as follows :

1. Package No.8 Bts. Kota Pariaman - Manggopoh AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 46.80 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As previously mentioned in the preceeding report, Contract Agreement has been executed on January 28, 2016 between the Government of Indonesia GOI and the winning responsive bidder, PT. PP Persero Tbk PT. Statika Mitra Sarana J.O for a contract amount of Rp. 355,500,000,000 and 720 calendar days contract time. Copy of the signed contract has been submitted to World Bank on February 17, 2016 for request of issuance of Form 384 for disbursement purpose and immediately a day after receipt of the copy on February 18, 2016, the Bank issued No Objection Letter NOL and Form 384. Notice To Proceed NTP to commence works is expected to be issued anytime during the month of March 2016.

2. Package No.10 Sp. Empat

Sp. Air Balam AWP-2 This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 61.70 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As all the issues and comments raised by the World Bank on the first submitted Bid Evaluation Report BER were all clarified and resolved, the revised Bid Evaluation Report has been resubmitted to the Bank on February 19, 2016, recommending the award of contract to the responsive and qualified bidder PT. Lancarjaya Mandiri AbadiPT. Cahaya Tunggal Abadi, JO in the amount of Rp.424,285,260,782.50 with 720 calendar days time completion. The revised Bid Evaluation Report BER has been cuncurred by the World Bank on February 22, 2016 by issuing a No Objection Letter NOL to award the contract to the joint operation of PT. Lancarjaya Mandiri Abadi and PT. Cahaya Tunggal Abadi. Western I ndonesia National Roads I mprovement Project 1 - 6

3. Package No.12 Kambang - Indrapura AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 55.20 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As previously mentioned in the preceeding report, Contract Agreement has been executed on January 28, 2016 between the Government of Indonesia GOI and the winning responsive bidder, PT. Lancarjaya Mandiri Abadi PT. Cahaya Tunggal Abadi JO for a contract amount of Rp. 358,650,400,000 and 720 calendar days contract time. Copy of the signed contract is still in process for submission to World Bank for request issuance of Form 384 for disbursement purpose.

4. Package No.16 Seblat-Ipuh AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 34.50 kilometers and is located in the Province of Bengkulu. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System. Bid Evaluation Report BER has been completed by POKJA and submitted to World Bank on January 11, 2016 for review and issuance of No Objection Letter NOL. However, per Bank s letter of January 20, 2016 regarding results of their prior review of the BER have comments on the proposed disqualification of five 5 lower priced bidders. In line with the Bank s comments a revised Bid Evaluation Report is still under preparation for resubmission to World Bank for review and issuance of no objection to award the contract.

5. Package No.14 Painan - Kambang AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled, the submission and opening of bids took place in Padang on January 5, 2016. There were four 4 applicant bidders 3 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the four 4 bidders with their respective bid prices : • PT. Yasa Patria Perkasa Conbloc, JO Rp. 214,602,400,000 • PT. Waskita Karya Rp. 239,449,604,000 • PT. Jaya Konstruksi Rp. 239,628,825,000 • PT. PP Rp. 249,277,000,000 The lowest canvassed bid is submitted by the joint venture operation of PT. Yasa Patria Perkasa and Conbloc with an amount of Rp. 214,602,400,000 which is 19.80