4.11 WINRIP DOC MPR CTC MPR No.38 2016 2 20160229 00347

Western I ndonesia National Roads I mprovement Project 4 - 6 The major work item which conributed to the huge negative slippage is the Aspahalt Pavement. To date only 7.46 out of the 70.65 component of whole works has been accomplished. However, in the event that the recently concluded Field Engineering results with proposed 90 calendar days time extension will be formally approved, the completion date will be moved forward to August 31, 2016. ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura Tapan The contract package just recently commenced on December 10, 2016. During the period from the issuance of Notice To Proceed NTP until end of this month, Contractor concentrated on the preparation for mobilization at site . To date, Routine Maintenance Work wherein 0.05 of the 0.20 work component and 0.54 from the 2.54 mobilization component have been done. ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko Based on the revised schedule due to approval of the results of Field Engineering , the actual overall progress attained by the Contractor up to end of this period is 33.04 against 36.74. At the end of the 12 th month of the contract period, Contractor s performance with respect to their work progress seem to be satisfactory as the negative slippage have been minimized to a single digit. For more details of the Contract Package, refer to ANNEX P-11 Executive Summary Report . Package No. 13 : Sp. Rukis Tj. Kemuning The current work progress showed sign of slowing down for the past two 2 months as only 0.60 combine output have been realized. At the end of the month, the overall work accomplished is 14.37 of the 20.36 schedule at month s end. The negative slippage suddenly dropped from -0.78 in the preceeding month to -5.99. The negative slippage is still manageable at the moment, provided the Contractor will take immediate actions on problems that are hampering the work progress. Barring any unforseen circumstances that will disrupt or interrupt the construction implementation, it is expected that the project can be completed on- time or even ahead of the schedule. Details of the work progress are shown in ANNEX P-13 Executive Summary Reports. Package No. 15: Sibolga Bts. Tapsel The contract package just recently commenced on November 20, 2015. During the period from the issuance of Notice To Proceed NTP until end of this month, Contractor concentrated on the preparation for mobilization at site . At the end of this reporting month February 29, 2016 actual overall progress achieved is 1.42 of the 3.18 schedule for the end of the month. During the month, the Contractor mainly concentrated on