Western I ndonesia National Roads I mprovement Project 1 - 7
below the approved Owner s Estimate OE of Rp. 267,590,800,000 while the 2
nd
lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate.
Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized upon receipt of responses from the bidders regarding
POKJA s letter of request for clarification of some issue from the bidders.
6. Package No.20 Lubuk Alung - Sicincin AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 14.60 kilometers and is located in the Province of West
Sumatera.
The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System.
As scheduled, the submission and opening of bids took place in Padang on January 5, 2016.
There were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation.
Following are the five 5 bidders with their respective bid prices : •
PT. Nindya Karya Rp. 113,818,300,000
• PT. Conbloc Infratechno
Statika, KSO Rp. 118,172,039,000
• PT. Waskita Karya
Rp. 122,767,255,000 •
PT. Jaya Konstruksi Rp. 126,670,765,000
• PT. PP
Rp. 125,192,900,000 The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of
Rp. 113,818,300,000 which is 13.32 below the approved Owner s Estimate OE of Rp. 131,302,200,000 while the 2
nd
lowest bid is quoted by PT. PT. Conbloc Infratechno Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00
lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee
and expected to be finalized upon receipt of responses from the bidders regarding POKJA s letter of request for clarification from the bidders.
7. Package No.21 Lubuk Alung - Kuraitaji AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West
Sumatera.
The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System.
As scheduled the submission and opening of bids took place in Padang on January 5, 2016.
There were eight 8 applicant bidders 7 sole entity and 1 joint venture operation who submitted bids for the civil works implementation.
Following are the eight 8 bidders with their respective bid prices : •
PT. Multi Structure Rp. 126,301,991,200
Western I ndonesia National Roads I mprovement Project 1 - 8
• PT. Adhi Karya
Rp. 133,638,300,000 •
PT. Nindya Karya Rp. 141,465,600,000
• Pan Asia Corporation
Rp. 143,186,229,000 •
PT. Conbloc Infratechno Statika, KSO
Rp. 143,227,420,000 •
PT. Jaya Konstruksi M,P Rp. 147,718,199,000
• PT. Waskita Karya
Rp. 150,966,239,000 •
PT. PP Rp. 154,124,000,000
The lowest canvassed bid is submitted by PT. Multi Structure with an amount of Rp. 126,301,991,200 which is 23.28 below the approved Owner s Estimate OE of
Rp. 164,692,268,000 while the 2
nd
lowest bid is quoted by PT. Adhi Karya with an amount of Rp. 133,638,300,000 or 18.82 lower than the Owner s Estimate.
Bid Evaluation Report BER has been finalized by the Procurement Committee and submitted to PMU for submission to World Bank. Copy of BER informally sent to
World Bank as advance copy
1.5
Procurement of Three 3 Consultancy Packages Under Category 3 of the Loan Agreement, Part 3: Road Sector Institutional Development
1. Technical Assistance for Capacity Building for Disaster Risk Reduction
The Technical Assistance for Disaster Risk Reduction was canceled based on the results of meeting between DGH and the WB on October 12, 2015. It was decided to
cancel the Technical Assistance and to be replaced by a Technical Assistance for Study on Slope Stabilization Design and Management under Loan Category-2.
Term of Reference TOR has already been finalized and submitted to World Bank for concurrence prior to publication on PU Website for Request of Expression of
Interest REOI from interested consulting firms.
2. Technical Assistance for Capacity Building for Environmental Management
Cancelled.
3. Technical Assistance for Capacity Building for Road Safety
Cancelled.