Western I ndonesia National Roads I mprovement Project 4 - 20
a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared.
b LARAP Implementation is underway for the remaining 18 PAP be allocated 2015 national budget and schedule to be settled on Dec 2015.
c Monitoring Report for the compensation payments of previously paid PAPs still to be prepared for submission to World Bank.
C. Update during this reporting month of February 2016 a Data of the payments to the 18 PAP Balance from 259 PAPs are under preparation by
Satker PJN I Bengkulu. b Updated LARAP documents submitted on February 22, 2016 to World Bank.
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak
Province : Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 •
Monitoring report for 154 of the total 2.273 PAPs was given No Objection Letter NOL on October 13, 2015.
• Monitoring report for 735 of the remaining 2.119 PAPs was given No Objection Letter NOL on
November 26, 2015 B. Pending Issues, Concern and Actions
a Monitoring Report for the compensation payments for the remaining 1.384 PAPs has to be submitted to World Bank.
C. Update during this reporting month of February 2016 a Compensation payments for the remaining 1.384 from 2.273 PAP have been already
released. b PMUCTC waiting data of payment progress for the remaining of 1.384 PAPs from Satker
PJN II Lampung.
18. Monitoring Report of the LARAP Package No.18
: Mukomuko Bts. Sumbar
Province : Bengkulu
Cancelled from the WINRIP Program.
19. Monitoring Report of the LARAP Package No.19
: Lais - Bintunan Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 for the LARAP
implementation. •
Monitoring report for 208 of the remaining 290 PAPs was given No Objection Letter NOL on November 26, 2015.
Western I ndonesia National Roads I mprovement Project 4 - 21
B. Pending Issues, Concern and Actions a Monitoring Report for payment of compensation to the remaining 82 PAPs still to be
prepared for submission to World Bank. C. Update during this reporting month of February 2016
a PMUCTC waiting data of payment progress for the remaining of 82 PAPs from Satker PJN I Bengkulu.
20. Monitoring Report of the LARAP Package No. 20
: Lubuk Alung - Sicincin Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions
a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of February 2016
a Local Government Satker PJN I Sumatera Barat has done socialization stage to PAPs stage first of land acquisition process during January 2016.
21. Monitoring Report of the LARAP Package No. 21
: Lubuk Alung - Kurataji Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions
a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of February 2016
a Local Government Satker PJN I Sumatera Barat has done socialization stage to PAPs stage first of land acquisition process during January 2016.