Western I ndonesia National Roads I mprovement Project 1 - 7
below  the  approved Owner s  Estimate  OE  of  Rp. 267,590,800,000 while  the  2
nd
lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate.
Bid Evaluation Report BER is under final preparation by the Procurement Committee and  expected  to be finalized upon  receipt  of  responses  from  the  bidders  regarding
POKJA s letter of request for clarification of some issue from the bidders.
6. Package No.20 Lubuk Alung - Sicincin AWP-3
The sub-project is  to  be  implemented  under  implementation  schedule  AWP-3.  The Project  road  lenght  covers  14.60  kilometers  and  is  located  in the  Province  of  West
Sumatera.
The  Contract  Package  is  procured  thru  post  qualification  criteria  and  National Competitive Bidding NCB using the Full e-Procurement System.
As scheduled, the submission and opening of bids took place in Padang on January 5, 2016.
There were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation.
Following are the five 5 bidders with their respective bid prices : •
PT. Nindya Karya Rp. 113,818,300,000
• PT. Conbloc Infratechno
Statika, KSO Rp. 118,172,039,000
• PT. Waskita Karya
Rp. 122,767,255,000 •
PT. Jaya Konstruksi Rp. 126,670,765,000
• PT. PP
Rp. 125,192,900,000 The  lowest  canvassed  bid  is  submitted  by  PT. Nindya Karya  with  an  amount  of
Rp. 113,818,300,000 which  is 13.32  below  the  approved Owner s  Estimate  OE  of Rp. 131,302,200,000 while the 2
nd
lowest bid is quoted by PT. PT. Conbloc Infratechno Statika,  KSO Joint  Operation  with  an  amount  of  Rp. 118,172,039,000 or 10.00
lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee
and  expected  to be finalized upon  receipt  of  responses  from  the  bidders  regarding POKJA s letter of request for clarification from the bidders.
7. Package No.21 Lubuk Alung - Kuraitaji AWP-3
The sub-project  is  to  be  implemented  under  implementation  schedule  AWP-3.  The Project  road  lenght  covers  16.80  kilometers  and  is  located  in  the  Province  of  West
Sumatera.
The  Contract  Package is  procured  thru  post  qualification  criteria  and  National Competitive Bidding NCB using the Full e-Procurement System.
As scheduled the submission and opening of bids took place in Padang on January 5, 2016.
There  were eight 8  applicant  bidders  7 sole  entity  and 1 joint  venture  operation who submitted bids for the civil works implementation.
Following are the eight 8 bidders with their respective bid prices : •
PT. Multi Structure Rp. 126,301,991,200