World Bank Implementation Review Mission and Site Visit

Western I ndonesia National Roads I mprovement Project 1 - 7 below the approved Owner s Estimate OE of Rp. 267,590,800,000 while the 2 nd lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized upon receipt of responses from the bidders regarding POKJA s letter of request for clarification of some issue from the bidders.

6. Package No.20 Lubuk Alung - Sicincin AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled, the submission and opening of bids took place in Padang on January 5, 2016. There were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the five 5 bidders with their respective bid prices : • PT. Nindya Karya Rp. 113,818,300,000 • PT. Conbloc Infratechno Statika, KSO Rp. 118,172,039,000 • PT. Waskita Karya Rp. 122,767,255,000 • PT. Jaya Konstruksi Rp. 126,670,765,000 • PT. PP Rp. 125,192,900,000 The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of Rp. 113,818,300,000 which is 13.32 below the approved Owner s Estimate OE of Rp. 131,302,200,000 while the 2 nd lowest bid is quoted by PT. PT. Conbloc Infratechno Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00 lower than the Owner s Estimate. Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized upon receipt of responses from the bidders regarding POKJA s letter of request for clarification from the bidders.

7. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As scheduled the submission and opening of bids took place in Padang on January 5, 2016. There were eight 8 applicant bidders 7 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the eight 8 bidders with their respective bid prices : • PT. Multi Structure Rp. 126,301,991,200