World Bank and GOI Compliance

Western I ndonesia National Roads I mprovement Project 6 - 3 No. Action By Whom Status and Target dates Updated Status January 26, 2016 reports to DGH 2015 28. Put the Mid-term review report on WINRIP website PMUCTC • December 20, 2016 • Done 29. Regularly submit the quarterly progress reports to the Bank PMU • Each calendar quarter • Noted

6.1.3 Performance Indicators

Key Performance Indicators are developed and agreed between the World Bank and GOI, and will be monitored over the whole project period the changes in variables will be calculated annually. The set indicators are describe in the project Appraisal Document PAD and the Loan Agreement between the GOI and the World Bank. The overall progress towards achieving the PDO of increasing the effective use of selected sections of national roads along the Western Sumatra Corridor by reducing road user costs is considered moderately satisfactory. Progress in implementation has picked up, and there has been an advance with respect to several project indicators. In addition, a project restructuring is being processed which should bring the project largely back on track. The PMU provided an update on the achievement of the indicator targets. There has been relatively good progress on three of the five intermediate indicators. For one of the remaining intermediate indicators on bridge improvement, progress is expected within the next semester. The last intermediate indicator related to institutional strengthening will be cancelled in the framework of project restructuring. For the PDO indicator on AADT, CTC carried out static traffic counts in March 2015 and confirmed that the original indicator targets are adequate. The mission refined a few indicators definitionsbaselines and updated some indicator targets to take into account the project implementation delays. These changes will be reflected in the upcoming project restructuring. From the baseline 2010 AADT and estimated AADT for the year 20142015, the extrapolated AADT for the year 2013 resulted to 11,254 vehicles per day or 8.8 above the targeted 10,347 vehicles per day in 2013. Shown in Table 11 is the comparison between target and actual estimated AADT. Table 11 Year Targeted AADT Estimated Baseline 2010 7,837 FY1 2013 target 10,347 FY1 2013 actual 11,254 FY2 2014 target 11,351 FY2 2014 actual 12,696 FY3 2015 target 12,453 FY4 2016 target 13,304 FY5 2017 end target 14,214 Western I ndonesia National Roads I mprovement Project 6 - 4

6.2 Implementation Support Components

6.2.1 Core Team Consultant CTC

The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, information management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of the anti-corruption action plan, support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation. The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. Epadascon Permata Engineering Consultant. The main CTC activities during February 2016 are as follows: • Conducted site inspections with TFAC mission on Packages 11 and 19. • Prepared Monthly and Bid EvaluationProcurement Reports for Packages 5 and 11. • Monitoring the implementations of the ESAMP, anti-corruption action plans, complains from project site, progress of LARAP, procurement activities and financial progress. • Prepared and issued various letters to PMU and DSC. • Submitted various Reports to PMU concerning environmental and the status of LARAP implementations. • Assisted the Procurement Committee POKJA of BALAI 2 in the evaluation of bids and preparation of Bid Evaluation ReportsBER for Packages 14, 20 and 21. • Monitored the actual construction progresses of the twelve 12 on-going contract packages and advised PMU of the current situations of the sub-projects. • Attended various meetings. • Site visit for technical review of road safety audit of package 01. • Finalized draft Amendment No.4 for CTC.

6.2.2 Design and Supervision Consultant DSC

The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of Engineer under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West Sumatera. Western I ndonesia National Roads I mprovement Project 6 - 5 DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March 2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.

6.2.3 Study on Slope Stabilization Design and Management

This component consists of technical assistance for analytical work of an alternative design for road segment that pass through critical environmental assets and vulnerable areas especially on slope protection design and management.

6.3 TRAINING TO SUPPORT PROJECT IMPLEMENTATION

The work during this reporting month is actually inseparable continuation of what were prepared and done during previous month January 2016 summarized below:  Continuing the preparation of some trainings to be implemented on the first opportunity.: o IFR Training was scheduled to be deliver on the 1 st week of March 2016; o PMM Application Training was scheduled on the 3 rd week of March 2016. o The RKPPL Training was scheduled on 2 nd week of April 2016.  Continuing to update the PMM and other training materials as required.  Continuing to ask for confirmation of the mobilization of contractors and consultants staff of the respective packages. The work during this reporting month was then focused on the following activities:

6.3.1 Continuing to prepare the implementation of three training programs that actually

should had been delivered in November-December last year; i.e:  The PMM Application Training 3, initially scheduled for being delivered on the end of November 2015, was postponed to mid of January 2016, and was then postponed again as the project decided that it would be no training implementation before March 2016 because of duty travel cost problem that required to be re-arranged. However, at the end of February the Training Team got information that the training could not be delivered yet in March 2016, still awaiting for the Amendment 4 process  The fourth 4 th IFR Training or Training on Preparing Interim un-audited Financial Report IFR for packages: 07 Indrapura Tapan, 12 Kambang-Indrapura, 08 Batas Kota Pariaman Manggopoh, and 10 Simpang Empat Sp. Air Balam was initially scheduled to be held on 2 nd week of December 2015. However, it was postponed by PMU to mid of January 2016, and then was postponed again to March 2016. Still has to wait for the Amendment 4 process. Western I ndonesia National Roads I mprovement Project 6 - 6  The seventh 7 th RKPPL Training was scheduled to be carried out in January 2016 However, at the end of December 2015, the project informed that all trainings would not be delivered earlier than March 2016, while awaiting the results of duty travel budget re- arrangement. and the process of Amendment 4. It still has to wait for the process of Amendment 4. As mentioned in previous reports, the delivery of some training programs had often been constrained, and resulted in postponement. Some of the constraints were noted as follows:  Delay of mobilization of consultants and contractors staff who would be the main target of the training;  The re-arrangement of the duty travel budget by the project, as well as the Amendment 4 have still been in process and the results should be waited; The work was then focused on preparation, updatingrevision, preparing training budget plan Amendment 4 etc.  Continue to prepare the implementation of those three training: modifying letter of invitation, checking the training materials, modifying the combination of packages involved as well as prospective participants as required in compliance with the CTC Timeline, identifying the suitable venues, etc. The delivery of the three trainings still has to wait the result of Amendment 4 process  Continuing to update the PMM related to the new organization structure of the Ministry of Public Works and Housing as well as the DGH,, new regulation, NCB procurement , and the experiences of implementing the project up to now.  Asking for confirmation of the mobilization of contractors and consultants in every package. It resulted, based of the Status of Civil Works, that only 3 packages of our training target that possibly could be addressed by our training at the end of this reporting month. ~ Package 07 : Indrapura Tapan, status : COW per 10 December 2015; ~ Package 08: Bts. Pariaman Manggopoh:: Contract Signed on 28 January 2016; ~ Package 12 : Kambang Indrapura; : Contract signed on 28 January 20126.  Assisting in revising the duty travel budget plan for 2016-2017, as well as completing the draft of Amendment 4 annexes as required. Included estimate cost of operational training activities.

6.3.2 Progress

o In terms of training delivery, no training was delivered during this reporting month, so that no one was trained during this time. o However, the preparation of the next training run better, some of the revisions of the PMM were done as required while awaiting for the new decree concerning for instant