Monitoring Report of the LARAP Package No. 8

Western I ndonesia National Roads I mprovement Project 4 - 16 A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • Monitoring Report No. 1 submitted to PMU on July 6, 2015. • World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1. B. Pending Issues, Concern and Actions a Monitoring Reports No.2 of the LARAP s implementation for the remaining 40 PAP from the 190 total PAP in Kab. Bengkulu Selatan to be submitted to World Bank. b Monitoring Report No.3 for compensation payments of PAPs in Kab. Kaur to be prepared and submitted to WB. C. Update during this reporting month of October 2015 a A report of the compensation payment for the 41 remaining PAP in Kab. Bengkulu Selatan already submitted to WB. b Compensation payments of affected persons in Kab. Kaur 3.106 PAPs is on-going completion.

14. Monitoring Report of the LARAP Package No. 14

: Painan - Kambang Province : Sumatera Barat A. Previous Status : • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. • LARAP s signed action plan was given No Objection Letter NOL by World Bank. B. Pending Issues, Concern and Actions a Inventory of affected assets and measurement by Land Acquisition Committe of the Local Government are completed. Appraisal to be done as soon as possible. C. Update during this reporting month of October 2015 a Appraisal process of affected assets is underway.

15. Monitoring Report of the LARAP Package No. 15

: Sibolga Bts. Tapsel Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. B. Pending Issues, Concern and Actions a 1065 from total 1448 PAP is under negosiationcompensation process. b Monitoring Report No.1 for LARAP implementation for compensation of 40 out of the 1448 PAP still to be prepared by SATKER RIN North Sumatra. C. Update during this reporting month of October 2015 a Monitoring Report No.1 for LARAP implementation for compensation of 40 out of