Western I ndonesia National Roads I mprovement Project 4 - 16
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank.
• Monitoring Report No. 1 submitted to PMU on July 6, 2015.
• World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring
Report No.1. B. Pending Issues, Concern and Actions
a Monitoring Reports No.2 of the LARAP s implementation for the remaining 40 PAP from the 190 total PAP in Kab. Bengkulu Selatan to be submitted to World Bank.
b Monitoring Report No.3 for compensation payments of PAPs in Kab. Kaur to be prepared and submitted to WB.
C. Update during this reporting month of October 2015 a A report of the compensation payment for the 41 remaining PAP in Kab. Bengkulu
Selatan already submitted to WB. b Compensation payments of affected persons in Kab. Kaur 3.106 PAPs is on-going
completion.
14. Monitoring Report of the LARAP Package No. 14
: Painan - Kambang Province
: Sumatera Barat
A. Previous Status : •
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents.
• LARAP s signed action plan was given No Objection Letter NOL by World Bank.
B. Pending Issues, Concern and Actions a Inventory of affected assets and measurement by Land Acquisition Committe of
the Local Government are completed. Appraisal to be done as soon as possible. C. Update during this reporting month of October 2015
a Appraisal process of affected assets is underway.
15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel
Province : Sumatera Utara
A. Previous Status : •
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction.
B. Pending Issues, Concern and Actions a 1065 from total 1448 PAP is under negosiationcompensation process.
b Monitoring Report No.1 for LARAP implementation for compensation of 40 out of the 1448 PAP still to be prepared by SATKER RIN North Sumatra.
C. Update during this reporting month of October 2015 a Monitoring Report No.1 for LARAP implementation for compensation of 40 out of
Western I ndonesia National Roads I mprovement Project 4 - 17
the 1448 PAP already submitted to WB. b Payments to the 1403 PAP Balance from 1448 PAPs are under preparation
16. Monitoring Report of the LARAP Package No.16
: Seblat - Ipuh Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 for LARAP
implementation. B. Pending Issues, Concern and Actions
a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to
be prepared. b LARAP Implementation is underway for the remaining 311 PAP be allocated 2015
national budget and schedule to be settled on August 2015. C. Update during this reporting month of October 2015
a 102 PAPs has been paid awaiting payment data from SATKER to be submitted to PMU.
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak
Province : Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 B. Pending Issues, Concern and Actions
a Monitoring Report for the compensation payments for the 154 PAPs has to be submitted to World Bank.
C. Update during this reporting month of October 2015 a Compensation payments for 965 PAP from total 2,273 have been already released.
Payments of the other PAP s are on-going. b Monitoring Report for the compensation payments for the 154 PAPs already
submitted to WBWorld Bank c Monitoring Report for the compensation payments for the 811 PAPs will be
submitted to WB on mid Nov 2015
18. Monitoring Report of the LARAP Package No.18
: Mukomuko Bts. Sumbar
Province : Bengkulu
The sub-project is proposed to be deleted from the WINRIP Program.
19. Monitoring Report of the LARAP Package No.19
: Lais - Bintunan Province
: Bengkulu
A. Previous Status :