Western I ndonesia National Roads I mprovement Project 4 - 14
a A monitoring report regarding compensation payment for 19 of the remaining 56 PAPs will be submitted to WB on Mid Nov 2015.
b Payments to the 35 PAP Balance from 56 PAPs are under preparation
7. Monitoring Report of the LARAP Package No. 7
: Indrapura - Tapan Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank.
B. Pending Issues, Concern and Actions a Inventory of assets and measurements by Land Acquisition committee of the Local
Government are completed. b Implementation cost of LARAP will be included by Local Government in the 2015
budget. C. Update during this reporting month of October 2015
a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are completed.
Affected assets appraisal result has been completed. PPKSatker being done negotiation stage regarding compensation
value.
8. Monitoring Report of the LARAP Package No. 8
: Bts. Pariaman - Manggopoh Province
: Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions
a Inventory of assets and measurements by Land Acquisition committee of the Local Government are completed.
b Implementation cost of LARAP to be paid from APBN Province 2015. C. Update during this reporting month of October 2015
a 839 of the 945 PAP in Kab. Agam has been paid. A monitoring report of the payment for 839 PAP will be submitted to WB middle Nov 2015.
b Completion of inventory of affected assets are underway in Kab. Padang Pariaman.
9. Monitoring Report of the LARAP Package No. 9
: Rantau Tijang Kota Agung
Province : Lampung
The sub-project is proposed to be deleted from the WINRIP Program.
10. Monitoring Report of the LARAP Package No. 10
: Sp. Empat Sp. Air Balam
Province : Sumatera Barat
Western I ndonesia National Roads I mprovement Project 4 - 15
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions
a Implementation cost of LARAP will be included by the Local Government in the 2015 budget.
b Inventory of affected assets and measurement by Land Acquisition committee of the Local Government are completed.
C. Update during this reporting month of October 2015 a Appraisal of affected assets for 1092 PAPs is completed.
b Local Government being done negotiation stage regarding compensation value
11. Monitoring Report of the LARAP Package No. 11
: Bantal - Mukomuko Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the
World Bank. B. Pending Issues, Concern and Actions
a Compensation payments for the remaining 123 PAP are on-going finalization. C. Update during this reporting month of October 2015
a 15 of the remaining 123 PAPs already received their compensation. A monitoring report will be submitted to WB on middle Nov 2015
b Payments to the 108 PAP Balance from 123 PAPs are under preparation.
12. Monitoring Report of the LARAP Package No. 12
: Kambang - Indrapura Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. B. Pending Issues, Concern and Actions
a Inventory of affected assets and measurement by Land Acquisition committee of the Local Government are completed.
b Implementation cost of LARAP will be included in APBN 2015. C. Update during this reporting month of October 2015
a Appraisal of affected assets are on going.
13. Monitoring Report of the LARAP Package No. 13
: Sp. Rukis Tj. Kemuning
Province : Bengkulu