Document Library System, used to record all information of document and
Western I ndonesia National Roads I mprovement Project 6 - 2
No .
Action By Whom
Updated Status Oct 19, 2015
Current Target Dates Sept 7, 2015
Update Status 16 Oct 2015
• Package 5
• Package 17
• Package 13
untuk 102 WTP secara informal
• End of Oct
2015 Berita acara relokasi 1
WTP akan terkirim ke WB
• End of Oct
2015 terkirim ke WB data
administrasi 231 WTP
• 15 Dec 2015
terkirim ke WB data
administrasi 1500 WTP
• End of Oct 2015
• Sep 14, 2015
• End of Sep 2015
• 1 PAP already relocated. 60
PAPs additional will be paid on Dec 2015
• Total 2.269 PAPs. 461 PAPs
already paid. The remaining PAPs will be paid on Dec 2015
• Total 3.295 PAPs. 189 PAPs
already paid. Half of the remaining PAPs will be paid in
2015 and the rest will be paid in 2016
3. Bidding process on disaster
management •
Send to Bank the revised ToR
• Re-announce the RFP
PMU and CTC •
Meeting on Oct 21, 2015
• A meeting with Subdit
LKJ will be held by 10 Sep 2015 to finalize
the ToR, the Tor will afterward be sent to
the Bank and the request for
manifestation published
•
4. •
Send bidding document Packages
20, 21
• Send bidding
document Packages 14, 16
PMU •
Langsung tender setelah
terima surat WB tanggal 20
Oct 2015 •
14 Sep 2015
• End of Sep 2015
• Draft Bid Document sent to
Balai II Package 20, 21, 14 for review. Will be sent to WB
approximately on the third week of Oct 2015
• Procurement process schedule
on the beginning of Nov 2015 •
SBD sent to Balai III Package 16. OE is waiting for approval
from DGH. Draft bid document will be sent to WB end of Oct
2015
• Procurement process schedule
on the mid of Nov 2015 5.
Package 2: Accelerate the processing of the
necessary contact modification, which needs
to cover all accesses to property and any time
extension and send it to the Bank if it is above 15
PMU •
Mid of Nov 2015 proposal
of variation order more
than 15 and time extension
• Need decision on
slope design to finalize the contract
modification request decision by end of
Sep 2015 •
Needed contract new modification regarding to
explanation package 2 in the row no. 2 above
6. Package 3: Send draft
amendment for package 3 19 for prior Bank no-
objection, which needs to cover all accesses to
property and DSC needs to push contractor to submit
soft drawing of cross section to propose
PMU •
Mid of Nov 2015
proposal of variation order
more than 15 and time
extension •
Need decision on slope design to
finalize the contract modification request
decision by end of Sep 2015
• Needed contract new
modification regarding to explanation package 3 in the
row no. 2 above
Western I ndonesia National Roads I mprovement Project 6 - 3
No .
Action By Whom
Updated Status Oct 19, 2015
Current Target Dates Sept 7, 2015
Update Status 16 Oct 2015
variation order 7.
Report back to the Bank on how DGH has
implemented the recommendations of the
auditors in the auditing report of the 2014 financial
statements partial response at least while
waiting for feedback from the Balai
PMU •
End of Oct 2015
• Sending partial report
P1, P2, P3 by 11 Sep 2015
• Sending full report by
end of Oct 2015 •
Partially Done
8. Send to the Bank a request
for modification of the contract with DSC
PMU •
Oct 21, 2015 •
Mid of Sep 2015 revised version of
request •
By Sep 8, 2015 clarify with the DSC PPK and
send to the Bank a response to the
questions raised in July
•
9. Send restructuring request
to the Bank Ministry of
Finance •
23 Oct 2015 send to DG
• PMU will send the
draft request to DG by Oct 23, 2015
• 10.
Send the response to the Bank on the TFAC reports
for packages 2 and 3 and the supervision mission
reports for package 1 and 4 Response in format
similar to EINRIP project
PMU •
Package 4 send on 23 Oct
2015 •
Package 2 and 3 review by
CTC •
Package 1 review by DSC
and will be sent on 26 Oct
2015 •
Sep 21, 2015 •
Needed report revision from PPK all packages
11. Organize formal
supervision mission for the project with
BappenasMoF
Bank PMU •
Kick off meeting Nov
10, 2015 •
Closing meeting TFAC
Nov 6, 2015 •
Wrap up meeting Nov
13, 2015 tentative
• Site visit TFAC
schedule on Oct 26,2015 to
Padang and Nov 2, 2015 to
Bengkulu
• Site Visit
SocialEnviron ment 27, 28,
29 Oct to Sibolga and
Nov 2 to Bengkulu and
Nov 4 to Lampung
• Mid-October 2015
•