While The Access to Funding

ANAO Report No.11 2014–15 The Award of Grants under the Clean Technology Program 82

3.25 In

the August 2012 guidance, departmental assessors were also advised to consider how the ‘competitiveness’ of the proposal could be improved through the removal of project costs from the application, with acceptance by the applicant, as follows: Where the figure is in this order, [Customer Service Managers] CSMs should critically review the project budget to see if the applicant has included costs that are not linked directly to generating carbon or energy emissions savings. The applicant should be advised to remove these costs and submit a revised budget, otherwise the application is unlikely to be competitive. It is important that the assessment includes your analysis of the various components of the application and the interactions the CSM has had with the applicant in these circumstances. Following discussion, if the estimated per tonne calculation still exceeds 80 and the applicant wishes to proceed, the CSM should give careful consideration as to whether the application should be recommended for support. The assessment will need to document the rationale behind the decision.

3.26 Further

guidance was issued to assessors in December 2012 noting that for ‘uncompetitive applications’ departmental assessors should:  remove activities that do not directly contribute to energy and carbon savings or do not represent value for money;  if still uncompetitive, look to see how far it is away from similar projects approved; and  include in the assessment that the company would be prepared to accept a reduced grant amount.

3.27 Eligible

activities could be an essential component of the project, but separable in circumstances where grant funds per tonne of carbon abated was considered, by the department, to be uncompetitive. This approach was reflected in guidance to assessors in March 2013, which noted: Applicants can improve the competitiveness of their project by removing any eligible activities that do not directly contribute to significant carbon savings. For example site preparation activities which are for the dominant purpose of supporting implementation of the emissions reduction measure can be eligible activities. However, such activities do not directly contribute to carbon and energy savings. ANAO Report No.11 2014–15 The Award of Grants under the Clean Technology Program 83

3.28 Specifically,

if an application was considered to be ‘uncompetitive’, the program management area of the department advised assessors to remove project costs in the first instance 98 and to then consider reducing the amount of grant funding sought. 99 Further guidance on reducing the grant amount was provided to assessors in March 2013 and noted that the IA committees considered that: the core of any project should have significant carbon and energy savings, and if the project overall is good value for money then a lower grant ratio is acceptable. However, if the project appears to be primarily about productivity gains and energy and carbon savings are only marginal, then a reduced grant ratio to achieve a good Merit Criterion 1 score is not likely to be acceptable. 100

3.29 In

this respect, there were:  34 applications that were reframed to improve the competitiveness of the project and were approved by the program delegate; and  22 applications that were reframed to improve the competitiveness of the project, but were not approved by the program delegate.

3.30 Of

the 34 applications that were approved, there were at least four cases in which integral components, such as pre‐project activities, were excluded from the project and two cases in which the grant amount was reduced to an acceptable amount. However, there were also applications for 98 For example, the assessment records in respect to one application stated as follows: ‘