However, The Access to Funding
3.17 Other
reasons for reframing applications included changes to project costs and to projects in instances where the application did not provide sufficient evidence to support the claims made in relation to a component of the project where that component was separable. A clear reason for changing the grant amount was not documented in respect to 13 of the reframed applications.3.18 The
department’s perspective on the reframing of applications was outlined to ANAO in October 2014, as follows: The Department acknowledges that the approach adopted is not suitable for all granting programs, but was considered appropriate for the Clean Technology Programs which involved investing in capital equipment. Applications and assessments contained objective information on the capital equipment, for example manufacturing specifications, energy audits and utility bills. This enabled individual emission reduction measures to be easily dissected for analysis. A ‘reframed project’ refers to a class of projects where the original scope of the project as submitted in the application was: changed by the Committee during the merit assessment process; or changed by the applicant, or by the Customer Service Manager in consultation and full agreement with the applicant, during the due diligence process before merit assessment by the Committee. 92 There were three applications that were reframed during the departmental assessment and the IA committee assessment. Therefore, a total of 77 applications were reframed to exclude expenditure that did not provide value for money. 93 This was suggested by the IA committee in May 2012. 94 Two of the 12 applications that were reframed up to the maximum grant ratio available to the applicant were not recommended by the IA committees because the application did not demonstrate that the total carbon savings over the life of the project would be commensurate with the level of investment. ANAO Report No.11 2014–15 The Award of Grants under the Clean Technology Program 79 Many of the projects included a number of different capital investment activities, often unrelated. Part of Innovation Australiaʹs consideration ofParts
» The After The Program Design
» The The Program Program Design
» The However, A Program Design
» The situation in relation to the programs was similar to that identified in
» The department accepted the subsequent recommendation made in the earlier
» The program guidelines and IA’s disclosure of interest guidelines set out
» Notwithstanding the requirements of IA disclosure of interest guidelines,
» There Further, Program Design
» The The Performance Program Design
» Effective In In Access to Funding
» Relatively Access to Funding
» Determining Access to Funding
» However, The Access to Funding
» Consistent Access to Funding
» Specifically, In Access to Funding
» In Consistent Access to Funding
» Cabinet In The Access to Funding
» Accordingly, The Reduction in Emissions
» The The Reduction in Emissions
» In This The Reduction in Emissions
» In November 2013, the department noted in a review of the programs that:
» For example, one applicant that received funding under the programs initially
» In The Reduction in Emissions
» Another Reduction in Emissions
» As In In Reduction in Emissions
» However, The Reduction in Emissions
» As The Reduction in Emissions
» The In Reduction in Emissions
» Further, Reduction in Emissions
» There This Reduction in Emissions
» Agreed. Reduction in Emissions
» The In In Advice to the Program Delegate and Funding Decisions
» In Advice to the Program Delegate and Funding Decisions
» Given Advice to the Program Delegate and Funding Decisions
» The The Advice to the Program Delegate and Funding Decisions
» In The Advice to the Program Delegate and Funding Decisions
» Further, following the then Government’s decision to bring forward the introduction
» From the information provided in paragraphs 5.9 and 5.10, it is clear that
» However, this indicator was inconsistently applied in assessing applications,
» A Advice to the Program Delegate and Funding Decisions
» In In In Advice to the Program Delegate and Funding Decisions
» Overall, Advice to the Program Delegate and Funding Decisions
» The Advice to the Program Delegate and Funding Decisions
» Following The Advice to the Program Delegate and Funding Decisions
» The most common reason recorded for not recommending an application
» As Against A Advice to the Program Delegate and Funding Decisions
» Nevertheless, Advice to the Program Delegate and Funding Decisions
» To Part Advice to the Program Delegate and Funding Decisions
» Part Advice to the Program Delegate and Funding Decisions
» The Reporting and Funding Distribution
» Website In Reporting and Funding Distribution
» Reporting In Reporting and Funding Distribution
» Publication The Reporting and Funding Distribution
Show more