ANAO Report No.11 2014–15 The Award of Grants under the Clean Technology Program
81
3.22 For
the applications that were reframed, the departmental assessment report
included:
variations to project scope, such as removing elements of a project that
were considered to be ineligible expenditure or not considered to
provide ‘value for money’ in terms of carbon abatement, as discussed
in paragraph 3.16;
alternative
scores calculated using various interpretations of the evidence
provided in support of carbon savings, such as a reduction in the
expected production levels; and
a revised grant amount.
Amending the cost of carbon abated
3.23 Consistent
with the department’s advice that its culture is to ‘assist businesses
to access our programs where possible’, the department worked with
the applicant to reframe the scope of projects that were ‘unlikely to be supported’
in their original form.
96
This approach blurred the line between departmental
officials assessing applications for the purpose of informing committee
recommendations and officials acting as advocates for projects.
97
3.24 One
of the ways in which the prospect of obtaining funding for an application
was improved was by reducing the fiscal cost of abatement, which was
referred to, in the assessment of applications, as grant funds per tonne of carbon
abated. However, the decision to reframe an application was subjective as
the scoring framework did not contain a benchmark or upper limit on grant funds
per tonne of carbon abated. In August 2012 six months into the programs,
the department advised its assessors that: With
input from the committee we are starting to gather a pool of knowledge about
how this criterion is being addressed by applicants. The current data would
suggest that an estimated per tonne calculation that exceeds 80 is unlikely
to represent value for money as savings of this magnitude are not commensurate
with the level of investment.
96 Reframing was also evident in decisions made by IA committees to remove components of projects
considered to be uncompetitive. 97
In this regard, the AusIndustry Customer Service Charter at the time of program launch noted that AusIndustry would provide customers ‘with guidance to enable them to submit a competitive
application or to receive their full entitlement’, but that AusIndustry could not ‘help a customer write their application, though we can suggest what aspects of an application might be improved’ or ‘act as
an advocate or referee for a project to a committee or third party’.
ANAO Report No.11 2014–15 The Award of Grants under the Clean Technology Program
82
3.25 In
the August 2012 guidance, departmental assessors were also advised to
consider how the ‘competitiveness’ of the proposal could be improved through
the removal of project costs from the application, with acceptance by the
applicant, as follows: Where
the figure is in this order, [Customer Service Managers] CSMs should critically
review the project budget to see if the applicant has included costs that
are not linked directly to generating carbon or energy emissions savings. The
applicant should be advised to remove these costs and submit a revised budget,
otherwise the application is unlikely to be competitive. It is important that
the assessment includes your analysis of the various components of the application
and the interactions the CSM has had with the applicant in these circumstances.
Following discussion, if the estimated per tonne calculation still
exceeds 80 and the applicant wishes to proceed, the CSM should give careful
consideration as to whether the application should be recommended for
support. The assessment will need to document the rationale behind the decision.
3.26 Further
guidance was issued to assessors in December 2012 noting that for
‘uncompetitive applications’ departmental assessors should:
remove
activities that do not directly contribute to energy and carbon savings
or do not represent value for money;
if still uncompetitive, look to see how far it is away from similar
projects approved; and
include
in the assessment that the company would be prepared to accept
a reduced grant amount.
3.27 Eligible
activities could be an essential component of the project, but separable
in circumstances where grant funds per tonne of carbon abated was considered,
by the department, to be uncompetitive. This approach was reflected
in guidance to assessors in March 2013, which noted: Applicants
can improve the competitiveness of their project by removing any eligible
activities that do not directly contribute to significant carbon savings. For
example site preparation activities which are for the dominant purpose of supporting
implementation of the emissions reduction measure can be eligible activities.
However, such activities do not directly contribute to carbon and energy
savings.