In Advice to the Program Delegate and Funding Decisions
5.8 In
another example, an assessment report presented to the IA committee identified three possible variations of a project, including one scenario in which the grant amount would be reduced. The IA committee members in attendance at the meeting scored the application using at least two of the three possible project variations, with two committee members scoring the original application using four merit criteria as the original grant amount requested was greater than 1.5 million and three committee members scoring the reduced funding scenario using three merit criteria as the reframed grant amount was less than 1.5 million. In this case, all scores, including the scores given against merit criterion four, were averaged to determine the overall merit score even though the final grant amount was less than 1.5 million.5.9 The
appropriateness of the scoring was documented as an ongoing concern of the IA committee members who, in February 2013 a year into the programs, noted that it was difficult to ‘determine if projects are meritorious in carbon savings or financial savings’. These concerns were reflected in the recommendations made to the program delegate with 53 applications that scored over 60 per cent in aggregate against the merit criteria not recommended by the IA committees. The high number of applications that were not recommended, despite receiving a merit score of more than 60 per cent, was a direct consequence of an informal benchmarking approach that was used to consider the grant funds per tonne of carbon abated indicator jointly developed by the IA committee and the department. 131 Specifically, as discussed in paragraph 3.24, the department issued guidance to its assessors in August 2012 advising: It was always envisaged that the extent of the reduction in carbon emissions intensity merit criterion one would be the most difficult to assess. However, to date 36 applications have been assessed and 30 applications worth 26.4 million have been approved under both programs. With input from the committee we are starting to gather a pool of knowledge about how this criterion is being addressed by applicants. The current data would suggest that an estimated per tonne calculation that exceeds 80 is unlikely to 131 The IA committee meeting minutes reflect that 72 applications were not approved as carbon savings were not considered to be commensurate with the investment. When this feedback was provided by the IA committees as the reason for the recommendation, the associated notes recorded that the size of the grant funds per tonne of carbon abated was a factor that was considered.Parts
» The After The Program Design
» The The Program Program Design
» The However, A Program Design
» The situation in relation to the programs was similar to that identified in
» The department accepted the subsequent recommendation made in the earlier
» The program guidelines and IA’s disclosure of interest guidelines set out
» Notwithstanding the requirements of IA disclosure of interest guidelines,
» There Further, Program Design
» The The Performance Program Design
» Effective In In Access to Funding
» Relatively Access to Funding
» Determining Access to Funding
» However, The Access to Funding
» Consistent Access to Funding
» Specifically, In Access to Funding
» In Consistent Access to Funding
» Cabinet In The Access to Funding
» Accordingly, The Reduction in Emissions
» The The Reduction in Emissions
» In This The Reduction in Emissions
» In November 2013, the department noted in a review of the programs that:
» For example, one applicant that received funding under the programs initially
» In The Reduction in Emissions
» Another Reduction in Emissions
» As In In Reduction in Emissions
» However, The Reduction in Emissions
» As The Reduction in Emissions
» The In Reduction in Emissions
» Further, Reduction in Emissions
» There This Reduction in Emissions
» Agreed. Reduction in Emissions
» The In In Advice to the Program Delegate and Funding Decisions
» In Advice to the Program Delegate and Funding Decisions
» Given Advice to the Program Delegate and Funding Decisions
» The The Advice to the Program Delegate and Funding Decisions
» In The Advice to the Program Delegate and Funding Decisions
» Further, following the then Government’s decision to bring forward the introduction
» From the information provided in paragraphs 5.9 and 5.10, it is clear that
» However, this indicator was inconsistently applied in assessing applications,
» A Advice to the Program Delegate and Funding Decisions
» In In In Advice to the Program Delegate and Funding Decisions
» Overall, Advice to the Program Delegate and Funding Decisions
» The Advice to the Program Delegate and Funding Decisions
» Following The Advice to the Program Delegate and Funding Decisions
» The most common reason recorded for not recommending an application
» As Against A Advice to the Program Delegate and Funding Decisions
» Nevertheless, Advice to the Program Delegate and Funding Decisions
» To Part Advice to the Program Delegate and Funding Decisions
» Part Advice to the Program Delegate and Funding Decisions
» The Reporting and Funding Distribution
» Website In Reporting and Funding Distribution
» Reporting In Reporting and Funding Distribution
» Publication The Reporting and Funding Distribution
Show more