As With Program Design
2.21 The
risk of funding projects that would have proceeded without government funding was not addressed in practice, as highlighted by the examples in Table 2.2. Table 2.2: Projects largely complete at the time of application submission 62 Case study Relevant extract from committee discussion Merit score Program delegate decision Grant amount 1 The company was going to do this anyway and had planned to do this two years ago, and this program came along and provided opportunity to get free money. 89.7120 Supported 9 500 000 2 Project was 85 complete at the time of application. 101.9120 Supported 9 100 000 3 Project was partially complete and is part of a 45 million project. It was not clear what benefits could be attributed to program funding. 78.4100 Supported 800 000 3 The company had a legal undertaking to do this project regardless of whether the Commonwealth provides funding. 72.0100 Supported 66 897 Source: ANAO analysis of departmental records.2.22 As
part of an internal review of the programs in November 2013, the department identified that: A consequence of no need‐for‐funding requirements is that some approved projects would have already been implemented without grant funding. In fact, some approved projects had already undergone internal final approvals and were already underway at the time of application.2.23 Although
in some cases there were significant periods of time between the date of lodgement of an application, decision and execution of a funding agreement, there were also: 25 funding agreements with grants totalling 6.5 million that were executed on or after the project end date listed in the funding agreement; and 62 This information was sourced from informal notes taken by staff during IA committee meetings. The lack of formalised transcripts explaining committee discussions is discussed paragraphs 2.47 to 2.60.Parts
» The After The Program Design
» The The Program Program Design
» The However, A Program Design
» The situation in relation to the programs was similar to that identified in
» The department accepted the subsequent recommendation made in the earlier
» The program guidelines and IA’s disclosure of interest guidelines set out
» Notwithstanding the requirements of IA disclosure of interest guidelines,
» There Further, Program Design
» The The Performance Program Design
» Effective In In Access to Funding
» Relatively Access to Funding
» Determining Access to Funding
» However, The Access to Funding
» Consistent Access to Funding
» Specifically, In Access to Funding
» In Consistent Access to Funding
» Cabinet In The Access to Funding
» Accordingly, The Reduction in Emissions
» The The Reduction in Emissions
» In This The Reduction in Emissions
» In November 2013, the department noted in a review of the programs that:
» For example, one applicant that received funding under the programs initially
» In The Reduction in Emissions
» Another Reduction in Emissions
» As In In Reduction in Emissions
» However, The Reduction in Emissions
» As The Reduction in Emissions
» The In Reduction in Emissions
» Further, Reduction in Emissions
» There This Reduction in Emissions
» Agreed. Reduction in Emissions
» The In In Advice to the Program Delegate and Funding Decisions
» In Advice to the Program Delegate and Funding Decisions
» Given Advice to the Program Delegate and Funding Decisions
» The The Advice to the Program Delegate and Funding Decisions
» In The Advice to the Program Delegate and Funding Decisions
» Further, following the then Government’s decision to bring forward the introduction
» From the information provided in paragraphs 5.9 and 5.10, it is clear that
» However, this indicator was inconsistently applied in assessing applications,
» A Advice to the Program Delegate and Funding Decisions
» In In In Advice to the Program Delegate and Funding Decisions
» Overall, Advice to the Program Delegate and Funding Decisions
» The Advice to the Program Delegate and Funding Decisions
» Following The Advice to the Program Delegate and Funding Decisions
» The most common reason recorded for not recommending an application
» As Against A Advice to the Program Delegate and Funding Decisions
» Nevertheless, Advice to the Program Delegate and Funding Decisions
» To Part Advice to the Program Delegate and Funding Decisions
» Part Advice to the Program Delegate and Funding Decisions
» The Reporting and Funding Distribution
» Website In Reporting and Funding Distribution
» Reporting In Reporting and Funding Distribution
» Publication The Reporting and Funding Distribution
Show more