Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 19 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the world bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.

6. Report of LARAP for Sp. Rampa - Poriaha

Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows: a. Moving and providing compensation for one person kiosk owner affected must including to the action plan. b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan c. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp. Rampa – Poriaha. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the world bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.

7. Report of Five Larap in Bengkulu

CTC recieved Larap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five of Larap reports consists Larap for Package No. 13: Sp. Rukis – Tanjung Kemuning, Larap for Package No. 6: Psr Pedati – Kerkap, Larap for Package No. 11: Muko-muko – Bantal, Larap for Package No. 16: Seblat – Ipuh, Larap for Package No. 16: Bintunan – Lais. CTC reviewed the five 5 Larap Reports, and already submitted to the world bank from PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province has reviewed by the World Bank Ref.WINRIP144 dated 20 November 2013 and need revision as follows: a. All five Larap reports that that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition and resettlement and need to budgeted. b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the inventory table do not show the situasion. According to world bank letter, PMU via Ref. 1476Bp.11MD2013 dated 27 November 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 20 to prepare the addresed above. Follow up the world bank review and PMU letter, now five Larap reports is being revision process by CTC. A revision for five Larap reports will be submitted to the world bank on the end of December 2013.

8. Report of LARAP for Sibolga – Bts Tapsel

CTC received Draft Final Larap report for Sibolga – Bts Tapsel from Balai dated 30 September 2013. The Larap report already submitted to the world Bank from PMU dated 22 October 2013, and approval the world bank dated 28 October 2013 Larap report for Sibolga – Bts Tapsel in North Sumatera Province has reviewed by the World Bank Ref.WINRIP140 dated 28 October 2013 and need revision as follows: d. There are some renters will be affected by the project which is also categoized as project affected people so must be recorded in the affected people list. e. There is a private grave will be affected by the project which eligible to get moving cost and ritual ceremony cost. f. There are 64 units of kiosks occupied side drain need to be displaced which get moving assistance in addition the compensation provided for their affected assets. According to world bank letter, PMU via Ref. 1404Bp.11MD2013 dated 31 October 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addresed above. Follow up the world bank review and PMU letter, now Larap reports is being revision process by CTC. A revision Larap reports will be submitted to the world bank on the end of December 2013.

9. Report of Three 3 LARAPS in West Sumatera

CTC received from Balai II Padang Draft Final of 3 Larap reports in West Sumatera consist Larap report of packages for Kambang - Indrapura, Bts Kota Pariaman – Manggopoh, and Sp Empat – Air Balam dated 01 August 2013. Review and comment from CTC has been sent to PMU dated 9 September 2013, and PMU has forwarded to P2JN Local Consultant with request to revise the LARAP report based on the CTC comment. However up to the end of November 2013 the revison of the 3 Larap reports has not been received CTC. CTC will suggest to PMUDirector of Implementation Affairs Region I to remind P2JNLocal Consultas to provide the revision for 3 Larap reports.

10. Report of Four 4 LARAPS in West Sumatera

Up to end of November 2013, CTC not yet received from Balai IIP2JN Padang 4 Larap reports in West Sumatera consist Larap report of packages for Indrapura – Tapan, Painan – Kambang, Lubuk Alung – Sicincin, and Lubuk Alung – Kuraitaji. CTC will suggest to PMUDirector of Implementation Affairs Region to remind Balai IIP2JN to provide the 4 Larap reports.