Package No. 12: Kambang – Indrapura Social Issues:- Package No. 13: Sp. Rukis – Tj. Kemuning Social Issues:-

Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 47 Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the end of December 2013. Environmental Issues:- CTC waiting for the UKLUPL document from P2JN Bengkulu

6.6.14. Package No. 14: Painan – Kambang Social Issues:-

The Larap report of package for Painan – Kambang is under preparation by Balai II Padang West Sumatera. Now CTC waiting for the report from Balai II Padang. Environmental Issues:- Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.15. Package No. 15: Sibolga – Bts. Tapsel Social Issues:-

CTC received Final LARAP report form BalaiPMU on 30 September 2013. The report was then submitted to the Bank on 22 October 2013 and approved by the Bank on 28 October 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the end of December 2013. Environmental Issues:- The UKLUPL was sent to Bank on 30 September 2013

6.6.16. Package No. 16: Sebelat – Ipuh Social Issues:-

CTC received Larap report form Balai III PalembangPMU dated 7 October 2013 and has reviewed a report and submitted to PMU dated 29 October 2013. The report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 48 Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the end of December 2013. Environmental Issues:- AMDAL document not yet complete, and CTC waiting for the report from P2JN Bengkulu.

6.6.17. Package No. 17: SP. Gunung Kemala – Pg. Tampak Social Issues:-

The Larap report has reviewed by CTC and submitted to PMU dated 30 August 2013. The report already submitted to the World Bank from PMU dated 10 September 2013 and approval the World Bank dated 16 September 2013 with some comment The revision of Larap Report submitted to PMU from CTC dated 29 October 2013. The report already submitted to the World Bank dated 06 November 2103 and responsed by the Bank on 12 November 2013 that the documents disclosed at PMU website. Environmental Issues:- The AMDAL was sent to Bank on 30 September 2013, and approved by the World Bank on 20 November 2013 and request the documents to disclosed at PMU website.

6.6.18. Package No. 18: Mukomuko – Bts. Sumbar Social Issues:-

This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear. Environmental Issues:- This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear.

6.6.19. Package No. 19: Lais - Bintunan Social Issues:-

CTC received Larap report form Balai III PalembangPMU dated 7 October 2013 and has reviewed a report and submitted to PMU dated 29 October 2013. The report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments.