Monthly Progress Report November 2013
Western I ndonesia National Roads I mprovement Project 35
Sibolga –
Batas Tapsel Coordination Meeting
Bidding Process in Padang
18 - 21 Nov Community
Development Officer Medan
Procurement Preparation and CRO’s Socialitation for Package
Simpang Rampa-Poriaha dan Sibolga
– Batas
Tapanuli Selatan
17 - 21 Nov Social
Impact Specialist
Bengkulu Attend the Plenary Meeting of
the Land
Acquisition and
Resettlement Activities on the National Roads Prop.
Bengkulu and
Monitoring Implementation LARAP Ipuh –
Bantal Section 18 - 20 Nov
Quality Assurance
Specialist Medan
Socialisation for
Quality Assurance and Discussion with
PPK of North Sumatra Province 22 - 23 Nov
Procurement Specialist Bandar
Lampung Pre Award Meeting for Road
Widening of Krui - Biha 29 - 30 Nov
Procurement Specialist Padang
Pre Contract Meeting for Bid Winner Package No. 3 :
Manggopoh – Pd Sawah
6.2.2 Design and Supervision Consultant DSC
The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of
‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs,
supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting.
The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required
results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and
continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai
II, and will be based in Padang, West Sumatra.
DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March
2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.
6.2.3 Road Sector Institutional Development
This component consists of technical assistance for capacity building for the new environmentrisk mitigation and road safety unit to enhance its capacity for disaster
risk assessment and planning, risk mapping of land-slides, coastal erosion, earthquake and floods, analysis of alternative road designs for road segments
passing through critical environmental assets and vulnerable areas.