Design Integration, Road Safety aspects and Monitoring of Environmental Studies

Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 18

4.6.2.2 Social Issues 1. Monitoring Report of the Larap for Krui - Biha

Larap report of the package for Krui Biha in Lampung Province already approved the World Bank dated 4 January 2013, and approval the monitoring report dated 18 April 2013. The pending issue is a partially affected mosque redevelopment. Local Governmentproject will rebuild affected mosque in parallel with construction work.

2. Monitoring Report of the Larap for Padang Sawah – Sp. Empat

Larap report of the package for Padang Sawah – Sp. Empat in West Sumatera Province already approved the World Bank dated 13 January 2013, and approval the monitoring report dated 19 July 2013. The pending issue is the remaining of 21 affected people not yet received compensation from Local Government. Now the compensation payment for 21 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready prior to contract signing.

3. Monitoring Report of the LARAP for Manggopoh – Padang Sawah

Larap report of the package for Manggopoh – Padang Sawah in West Sumatera Province already appoved the World Bank dated 4 January 2013, and approval the monitoring reports dated 18 April 2013. A report for the remaining of 22 affected people is under preparation by Local Government. The pending issue is the remaining of 15 affected people not yet received compensation from Local Government. Now the compensation payment for 15 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready prior to contract signing.

4. Monitoring Report of the LARAP for Ipuh – Bantal

Larap report of the package for Ipuh – Bantal in Bengkulu Province was approved the World Bank dated 10 December 2012. Up to the end of November 2013 CTC just receive a proof of compensation payment for 19 of the total 217 affected peoples. A monitoring report will be submitted to WB if ready prior to contract signing.

5. Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Larap report of the package for Sp. Gunung Kemala – Pugung Tampak in Lampung Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need revision as follows: a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data. b. Action plan table should include a formation of the land apprasing team, b moving 83 units of electricity utilities. c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanantion some data with no name in the nominative list. e. Action plan signewd by the relevan local government as a commitment that the local government will provide proper budget for the action plan f. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 19 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the world bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.

6. Report of LARAP for Sp. Rampa - Poriaha

Larap report for Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 and need revision as follows: a. Moving and providing compensation for one person kiosk owner affected must including to the action plan. b. Action plan signed by the relevan local government as a commitment that the local government will provide proper budget for the action plan c. Implementation monitoring report by using the form provided in the LARAP. According to world bank letter, PMU via Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the addressed above. Follow up the world bank review and PMU letter, CTC revised the Larap report for Sp. Rampa – Poriaha. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the world bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website.

7. Report of Five Larap in Bengkulu

CTC recieved Larap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five of Larap reports consists Larap for Package No. 13: Sp. Rukis – Tanjung Kemuning, Larap for Package No. 6: Psr Pedati – Kerkap, Larap for Package No. 11: Muko-muko – Bantal, Larap for Package No. 16: Seblat – Ipuh, Larap for Package No. 16: Bintunan – Lais. CTC reviewed the five 5 Larap Reports, and already submitted to the world bank from PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province has reviewed by the World Bank Ref.WINRIP144 dated 20 November 2013 and need revision as follows: a. All five Larap reports that that there are some assets land and building that will be affected entirely. Following the LARPF WINRIP should be covered on land acquisition and resettlement and need to budgeted. b. On the Larap report for package for Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the inventory table do not show the situasion. According to world bank letter, PMU via Ref. 1476Bp.11MD2013 dated 27 November 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK