Package No. 04: Ipuh – Bantal Package No. 05: Sp. Rampa – Poriaha

Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 45

6.6.6. Package No. 06: Ps. Pedati – Kerkap

Social Issues:- CTC received Larap report form Balai III PalembangPMU dated 7 October 2013 and has reviewed a report and submitted to PMU dated 29 October 2013. The report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the end of December 2013. Environmental Issues:- The UKLUPL was sent to Bank on 30 September 2013

6.6.7. Package No. 07: Indrapura – Tapan

Social Issues:- The Larap report of package for Indrapura – Tapan is under preparation by Balai II Padang West Sumatera. Now CTC waiting for the report from Balai II Padang. Environmental Issues:- Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.8. Package No. 08: Bts Kota Pariaman – Manggopoh

Social Issues:- CTC received the LARAP report form Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JN Local Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.9. Package No. 09: Rantau Tijang – Kota Agung

Social Issues:- This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear. Environmental Issues:- This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear. Monthly Progress Report November 2013 Western I ndonesia National Roads I mprovement Project 46

6.6.10. Package No. 10: Sp. Empat – Air Balam Social Issues:-

CTC received the LARAP report from Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JNLocal Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.11. Package No. 11: Bantal - Mukomuko Social Issues:-

CTC received Larap report form Balai III PalembangPMU dated 7 October 2013 and has reviewed a report and submitted to PMU dated 29 October 2013. The report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the end of December 2013. Environmental Issues:- AMDAL document not yet complete, and CTC waiting for the report from P2JN Bengkulu

6.6.12. Package No. 12: Kambang – Indrapura Social Issues:-

CTC received the LARAP report form Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JN Local Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- Now CTC waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.13. Package No. 13: Sp. Rukis – Tj. Kemuning Social Issues:-

CTC received Larap report form Balai III PalembangPMU dated 7 October 2013 and has reviewed a report and submitted to PMU dated 29 October 2013. The report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments.