Package No. 03: Manggopoh – Padang Sawah Social Issues:-

Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 47 According to the World Bank request, CTC revise a monitoring report, and submit to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank from PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people not yet received compensation from Local Government. Now CTC waiting a proof of the compensation payment for 15 affected people from local government. A construction could be done when a monitoring report already received the WB. Environmental Issues:- CTC a waiting for a SPPL report from Balai II Padang

6.6.4. Package No. 04: Ipuh – Bantal Social Issues:-

The Larap report of package for Ipuh – Bantal was approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of 217 PAPs from Head of Satker PJN II Bengulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank dated 24 December 2013, and now waiting a comment from the World Bank. Environmental Issues:- CTC a waiting responds from the Subdit TLKJ for environmental safeguard status UKLUPL for package Ipuh – Bantal.

6.6.5. Package No. 05: Sp. Rampa – Poriaha Social Issues:-

The Larap report of package for Sp. Rampa – Poriaha North Sumatera Province has already submitted to the World Bank from PMU dated 30 August 2013. The World Bank has reviewed the report dated 16 September 2013 require revision to be provided by DGH. According to the World Bank request, CTC revise a Larap report, and submit to PMU dated 29 October 2013. Larap report has been submitted to the World Bank from PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013 that the documents disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of Satker II Lampung Province. Environmental Issues:- PMU has been send the UKLUPL to the World Bank on 30 September 2013. Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 48

6.6.6. Package No. 06: Psr. Pedati – Kerkap Social Issues:-

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report will be submitted to the World Bank on the early of January 2014. Environmental Issues:- PMU has been send the UKLUPL to the World Bank on 30 September 2013.

6.6.7. Package No. 07: Indrapura – Tapan Social Issues:-

The Larap report of package for Indrapura – Tapan is under preparation by Balai II Padang West Sumatera. Now CTC waiting for the report from Balai II Padang. Environmental Issues:- AMDAL documents not yet finish, the CTC push the AMDAL consultant to finalize the AMDAL report as soon as possible.

6.6.8. Package No. 08: Bts Kota Pariaman – Manggopoh Social Issues:-

CTC received the LARAP report from Balai II PadangPMU dated 01 August 2013. Review and comment from CTC was sent to PMU dated 9 September 2013, and PMU forward to P2JNLocal Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- Environmental issues will integrated to design

6.6.9. Package No. 09: Rantau Tijang – Kota Agung Social Issues:-

This package will be substituted with other link by DGH, so the social safeguard requirement is not yet clear. Environmental Issues:- This package will be substituted with other link by DGH, need safeguard screening for new link proposed.