Package No. 09: Rantau Tijang – Kota Agung Social Issues:-

Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 49

6.6.10. Package No. 10: Sp. Empat – Air Balam Social Issues:-

CTC received the LARAP report from Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JNLocal Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- Environmental issues will integrated to design

6.6.11. Package No. 11: Bantal - Mukomuko Social Issues:-

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report will be submitted to the World Bank on the early of January 2014. Environmental Issues:- AMDAL documents not yet finish, the CTC push the AMDAL consultant to finalize the AMDAL report as soon as possible

6.6.12. Package No. 12: Kambang – Indrapura Social Issues:-

CTC received the LARAP report form Balai II PadangPMU on 01 August 2013. Review and comment from CTC was sent to PMU on 9 September 2013, and PMU forward to P2JN Local Consultant with request to revise the LARAP report based on CTC comment. Environmental Issues:- AMDAL documents not yet finish, the CTC push the AMDAL consultant to finalize the AMDAL report as soon as possible

6.6.13. Package No. 13: Sp. Rukis – Tj. Kemuning Social Issues:-

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 50 report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report will be submitted to the World Bank on the early of January 2014. Environmental Issues:- Environmental issues will integrated to design 6.6.14.Package No. 14: Painan – Kambang Social Issues:- The Larap report of package for Painan – Kambang is under preparation by Balai II Padang West Sumatera. Now CTC waiting for the report from Balai II Padang. Environmental Issues:- AMDAL documents not yet finish, the CTC push the AMDAL consultant to finalize the AMDAL report as soon as possible.

6.6.15. Package No. 15: Sibolga – Bts. Tapsel Social Issues:-

CTC received Final LARAP report form BalaiPMU on 30 September 2013. The report already submitted to the Bank on 22 October 2013 and approved by the Bank on 28 October 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision for the report will be submitted to the World Bank on the early of January 2014. Environmental Issues:- Environmental issues will integrated to design

6.6.16. Package No. 16: Sebelat – Ipuh Social Issues:-

CTC received a Larap report of package for Pasr. Pedati – Kerkap from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalization the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report will be submitted to the