Current status of the project for technical field as of 31 December 2013.

Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 46 6.6 Environmental and Social Impact Issues 6.6 Environmental and Social Impact Issues 6.6.1 Package No. 01: Krui – Biha Social Issues:- The LARAP report of package for Krui – Biha in Lampung Province has already approved by the World Bank dated 4 January 2013, and the monitoring report has been submitted to the World Bank from PMU dated 10 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH. According to the World Bank request, CTC revised a monitoring report, and submit to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank from PMU dated 21 June 2013, and approval from the World Bank dated 26 June 2013. Based on this progress, contract signing for the package can be done. Environmental Issues:- PMU has been send the SPPL to the World Bank on 30 September 2013.

6.6.2. Package No. 02: Padang Sawah – Simpang Empat. Social Issues:-

The Larap report of package for Padang Sawah – Simpang Empat West Sumatera Province has already approved by the World Bank dated 13 January 2013, and the monitoring report has been submitted to the World Bank from PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH. According to the World Bank request, CTC revise a monitoring report, and submit to PMU dated 5 July 2013. A monitoring report has been submitted to the World Bank from PMU dated 15 July 2103, and approval from the World Bank dated 19 July 2013. The project has the remaining of 21 affected people not yet received compensation from Local Government. Now CTC waiting a proof of the compensation payment for 21 affected people from local government. A construction could be done when a monitoring report already received the WB. Environmental Issues:- CTC a waiting for a SPPL from Balai II Padang

6.6.3. Package No. 03: Manggopoh – Padang Sawah Social Issues:-

The Larap report of package for Manggopoh - Padang Sawah West Sumatera Province has already approved by the World Bank dated 4 January 2013, and the monitoring report has been submitted to the World Bank from PMU dated 2 April 2013. The World Bank has reviewed the report dated 18 April 2013 require revision to be provided by DGH. Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 47 According to the World Bank request, CTC revise a monitoring report, and submit to PMU dated 18 June 2013. A monitoring report has been submitted to the World Bank from PMU dated 21 June 2103, and approval from the World Bank dated 26 June 2013. The project has the remaining of 15 affected people not yet received compensation from Local Government. Now CTC waiting a proof of the compensation payment for 15 affected people from local government. A construction could be done when a monitoring report already received the WB. Environmental Issues:- CTC a waiting for a SPPL report from Balai II Padang

6.6.4. Package No. 04: Ipuh – Bantal Social Issues:-

The Larap report of package for Ipuh – Bantal was approved by the World Bank dated 10 December 2012. CTC collected the compensation payment for 157 from the total of 217 PAPs from Head of Satker PJN II Bengulu Province during 18 – 19 December 2013. A monitoring report of the package for Ipuh – Bantal already submitted to the World Bank dated 24 December 2013, and now waiting a comment from the World Bank. Environmental Issues:- CTC a waiting responds from the Subdit TLKJ for environmental safeguard status UKLUPL for package Ipuh – Bantal.

6.6.5. Package No. 05: Sp. Rampa – Poriaha Social Issues:-

The Larap report of package for Sp. Rampa – Poriaha North Sumatera Province has already submitted to the World Bank from PMU dated 30 August 2013. The World Bank has reviewed the report dated 16 September 2013 require revision to be provided by DGH. According to the World Bank request, CTC revise a Larap report, and submit to PMU dated 29 October 2013. Larap report has been submitted to the World Bank from PMU dated 6 November 2103, and approval from the World Bank dated 12 November 2013 that the documents disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC is waiting report of implementation of the Larap from Head of Satker II Lampung Province. Environmental Issues:- PMU has been send the UKLUPL to the World Bank on 30 September 2013.