Package No. 12: Kambang – Indrapura Social Issues:-
Monthly Progress Report December 2013
Western I ndonesia National Roads I mprovement Project 50
report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank from PMU dated 13 November
2103 and approval the World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revision process by CTC. A revision of the Larap report will be submitted to the
World Bank on the early of January 2014.
Environmental Issues:-
Environmental issues will integrated to design
6.6.14.Package No. 14: Painan – Kambang Social Issues:-
The Larap report of package for Painan – Kambang is under preparation by Balai II Padang West Sumatera. Now CTC waiting for the report from Balai II Padang.
Environmental Issues:-
AMDAL documents not yet finish, the CTC push the AMDAL consultant to finalize the AMDAL report as soon as possible.