Design Integration, Road Safety aspects and Monitoring of

Monthly Progress Report December 2013 Western I ndonesia National Roads I mprovement Project 19

2. Monitoring Report of the Larap for Padang Sawah – Sp. Empat

Larap report of the package for Padang Sawah – Sp. Empat in West Sumatera Province already approved the World Bank dated 13 January 2013, and approval the monitoring report dated 19 July 2013. The pending issue is the remaining of 21 affected people not yet received compensation from Local Government. Now the compensation payment for 21 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready prior to contract signing.

3. Monitoring Report of the LARAP for Manggopoh – Padang Sawah

Larap report of the package for Manggopoh – Padang Sawah in West Sumatera Province already appoved the World Bank dated 4 January 2013, and approval the monitoring reports dated 18 April 2013. A report for the remaining of 22 affected people is under preparation by Local Government. The pending issue is the remaining of 15 affected people not yet received compensation from Local Government. Now the compensation payment for 15 affected people is being resolved by local government. A monitoring report will be submitted to WB if ready prior to contract signing.

4. Monitoring Report of the LARAP for Ipuh – Bantal

LARAP report of the package for Ipuh – Bantal in Bengkulu Province was approved the World Bank dated 10 December 2012. Up to the end of December 2013 CTC just receive a proof of compensation payment for 19 of the total 217 affected peoples. A monitoring report will be submitted to WB if ready prior to contract signing.

5. Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung

Tampak LARAP report of the package for Sp. Gunung Kemala – Pugung Tampak in Lampung Province has reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 and need revision as follows: a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data. b. Action plan table should include a formation of the land apprasing team, b moving 83 units of electricity utilities. c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanantion some data with no name in the nominative list. e. Action plan signewd by the relevan local government as a commitment that the local government will provide proper budget for the action plan f. Implementation monitoring report by using the form provided in the LARAP.